With the goal of ensuring progress, many key projects in Ha Tinh still maintain the construction pace throughout the New Year. Officers, engineers, and workers take the joy of the New Year as inspiration to complete the items soon.
Dai Hiep Company mobilizes machinery and human resources to construct the access road to the Dien Chau - Bai Vot expressway intersection.
Entering the New Year holiday, Ha Tinh is still affected by cold air, with drizzle, chilly weather and fog. Although it is the New Year holiday and the weather is not favorable, at the construction site of the North-South expressway project in the East phase 2017-2020, Dien Chau - Bai Vot section through Duc Tho district (Ha Tinh), contractors are arranging human resources, machinery and equipment to urgently carry out construction.
Engineer Vuong Dao Chau - Dai Hiep Company Limited shared that the unit is implementing the construction of crushed stone aggregate layer for the road foundation. As soon as the crushed stone aggregate is spread, the road roller will roll it many times to ensure the technique. The time to complete the items of the Dien Chau - Bai Vot expressway project is not much left (May 2024), so, although it is during the New Year holiday, the unit still arranges 100% of human resources and construction machinery with the goal of ensuring the project is implemented on schedule.
“Recently, the unit has opened the technical section of the overpass on Highway 8, contributing to making traffic more convenient for people than before. We are also continuing to focus on speeding up the remaining sections,” informed engineer Vuong Dao Chau.
Workers constructing Hung Duc bridge over Lam river during New Year holiday.
Meanwhile, at the Hung Duc bridge, which is over 4km long and crosses the Lam River connecting Hung Nguyen district (Nghe An) with Duc Tho district (Ha Tinh) - one of the items of the Dien Chau - Bai Vot expressway project, the joint venture of contractors Cienco 4, Hoa Hiep, Thai Yen, Dai Hiep... also made efforts to mobilize maximum human resources and machinery to concentrate on construction. According to engineer Tong Tran Hung - Construction site commander of Hoa Hiep Company Limited, although it is during the New Year holiday, the unit still maintains 100% of engineers and workers to carry out construction as usual. Up to this point, the unit has basically completed casting the super T beams, installed the basic spans and is implementing the construction of the bridge railings.
In addition to the Dien Chau - Bai Vot section, Ha Tinh is also implementing the construction of 3 component projects of the North - South Eastern Expressway in the 2021 - 2025 period, namely Bai Vot - Ham Nghi, Ham Nghi - Vung Ang and Vung Ang - Bung. During the New Year holiday, the bustling and urgent working atmosphere was maintained regularly by the contractor at the construction site.
Working atmosphere at the construction site of the North-South expressway project through Ha Tinh on the first day of the new year.
Mr. Ho Ngoc Loan - Deputy Director of Thang Long Project Management Board - investor of the two expressway sections Bai Vot - Ham Nghi, Ham Nghi - Vung Ang said: According to the original plan, the project was to be completed by the end of 2025 to be put into operation from 2026, however, Prime Minister Pham Minh Chinh is requesting to shorten the progress by 7 months, so the unit directed the contractor to speed up the construction progress. During the New Year, contractors are focusing on maximum human resources and equipment, dividing into "3 shifts, 4 teams" to work with the goal of shortening the project progress.
To meet the trial operation schedule by the end of 2024, the Vung Ang II Thermal Power Plant Project also organized construction throughout the New Year. Despite many difficulties, the construction teams at the site all made efforts to overcome difficulties to ensure construction and installation safety and quality.
When operating, the Vung Ang II Thermal Power Plant Project will contribute about 7.8 billion kWh/year to the national grid, creating jobs for about 250 workers.
Mr. Tran Thanh Cong - Director of Project Department of Vietnam Machinery Installation Corporation said: "We are in charge of installing the main mechanical items of Vung Ang II Thermal Power Plant including 70,830 new equipment and steel structures, 196,133 ID technological pipes. The item has been deployed since August 2022, and has completed about 70% of the volume. Currently, the unit is focusing on installing and completing the pressure systems of the boiler and turbine packages to be able to complete and reach the pressure testing milestone of the HP-MP packages of boiler No. 1 in January 2024. More than 800 officers, engineers, and workers working on the packages proactively registered to work through Tet to ensure the overall progress of the project".
Similarly, engineer Nguyen Anh Duc - Head of Construction Department, Doosan Enerbility Vietnam Company also excitedly shared: "Doosan is the general contractor of Vung Ang II Thermal Power Company Limited, so our unit has a great responsibility in completing the project progress. Currently, the important items of the package are all completed on time and ahead of schedule. We are focusing on completing the installation of equipment to put Unit 1 into trial operation on schedule.
As a multinational general contractor, we put construction safety first, while ensuring the progress and quality as committed to the investor. The biggest difficulty that the unit had to overcome to put the two generators into trial operation on schedule was the weather. Having to work continuously in rainy and windy weather conditions, we had to come up with many safety solutions to ensure that the construction work was not interrupted and met the set goals."
Although the weather was unfavorable during the holidays, the construction teams at the Vung Ang II Thermal Power Plant site made every effort to ensure safety and quality in construction and installation.
It is known that, up to this point, Vung Ang II Thermal Power Plant has completed more than 71% of the work volume, with a total disbursement value of over 33 trillion VND. The project board and the construction units have proactively encouraged and motivated workers to stay and work during Tet. The general contractor and contractors have agreed that workers who stay and work during Tet will be paid according to regulations (3 times higher than normal working days).
The Xuan Dieu extended road project in Ha Tinh city maintains more than 70% of its workforce compared to normal days.
In Ha Tinh city, the Xuan Dieu extended road project is one of the key projects with a total investment of 234 billion VND. Not only do workers work during the holidays, but they are also willing to work through lunch or at night to ensure the set progress.
Mr. Nguyen Cao Thang - technical officer of Khanh Mon Construction Company Limited said that the route is 1.8 km long and will be implemented from September 2023. During this period, the contractor is focusing on constructing the longitudinal drainage system, the horizontal culvert system: box culvert, round culvert, technical culvert and casting components. Due to the specificity of constructing the body and floor systems of the horizontal culverts, which require continuity, workers have divided into shifts to work through lunch and at night. During these holidays, the labor rate on the construction site remains at more than 70% compared to before. The company has tried to arrange suitable work and at the same time supported part of the cost to encourage and motivate workers.
Van Duc - Duong Chien
Source