Hundreds of workers "brave" the sun, diligently working on the Van Phong - Nha Trang highway
Friday, April 19, 2024 09:34 AM (GMT+7)
These days at the Van Phong - Nha Trang highway construction site, hundreds of workers and engineers are still working hard.
Workers and engineers of Son Hai Group are still working hard, the work is divided into many different teams, but most of the atmosphere on the construction site is cheerful and everyone is excited.
Son Hai is organizing construction at the site in 3 shifts, 4 teams continuously with construction teams, working around the clock with about more than 700 workers working.
Engineer Nguyen Thanh Dong (Son Hai Group) said that workers and machines have been working continuously these past few days. Today alone (10th of the third lunar month), more than 700 workers and 300 machines of all kinds are still working continuously at the construction site. The company always ensures the diet and encourages the workers, so everyone is happy to work.
Despite the extremely hot weather, workers at the Van Phong - Nha Trang highway construction site still work in shifts continuously.
According to engineer Nguyen Thanh Dong, it is expected that the contract package implemented by Son Hai on the Van Phong - Nha Trang expressway will be completed earlier than planned, currently 8 bridges and 25 civil tunnels are basically completed.
Son Hai Group workers worked through the holidays to beat the project's schedule. The project was divided into two main packages. Package XL.02 was implemented by a consortium of Son Hai Group Co., Ltd. and Vietnam Construction and Import-Export Joint Stock Corporation; the contract construction period was 34 months.
The North-South Expressway construction investment component project, Van Phong - Nha Trang section, was approved by the Ministry of Transport in Decision No. 910/QD-BGTVT dated July 13, 2022. The project is invested by Project Management Board 7 (Ministry of Transport). The level 1 road traffic project has a total investment of more than VND 11,808 billion, using the State budget.
The weather at the construction site is very hot at this stage.
Son Hai Group drivers are working at the construction site.
The project has a total route length of 83.35 km; the starting point is at Km285+000 connecting the southern entrance road of Co Ma tunnel, in Van Ninh district; the end point is at Km368+350 connecting the starting point of the expressway construction investment component project, Nha Trang - Cam Lam section, through Khanh Hoa province.
Cong Tam