TPO - After nearly 2 years of construction, the Le Quang Dao extended road project connecting Nam Tu Liem district with Ha Dong (Hanoi) has taken shape but did not ensure the progress of opening to traffic on the occasion of the 70th anniversary of the Liberation of the Capital (October 10). The Nam Tu Liem District Construction Investment Project Management Board said that the progress and quality of the project were affected by the weather, especially prolonged rain.
TPO - After nearly 2 years of construction, the Le Quang Dao extended road project connecting Nam Tu Liem district with Ha Dong (Hanoi) has taken shape but did not ensure the progress of opening to traffic on the occasion of the 70th anniversary of the Liberation of the Capital (October 10). The Nam Tu Liem District Construction Investment Project Management Board said that the progress and quality of the project were affected by the weather, especially prolonged rain.
The progress and quality of Le Quang Dao route are affected by the weather, especially prolonged rain... |
The project to build the extended Le Quang Dao route, from Thang Long Avenue in Nam Tu Liem District to the boundary of Duong Noi Urban Area in Ha Dong District (Hanoi City) has a total investment of more than 700 billion VND, with the People's Committee of Nam Tu Liem District as the investor. |
The project has an investment of about 740 billion VND, expected to be completed on the occasion of the 70th anniversary of the Liberation of the Capital (October 10). However, due to the project's poor progress, it cannot be opened to traffic in October. |
The Nam Tu Liem District Construction Investment Project Management Board said that due to the great impact of heavy rain, the progress could not be achieved as planned. |
Currently, the construction site is still bustling, the contractors are committed to completing related items, putting the project into use in December if the weather conditions are favorable. Currently, the units are focusing on constructing the final section of the route bordering Ha Dong. |
With a total length of more than 2.6 km, the route has a site clearance cost of more than 163 billion VND and a construction cost of more than 408 billion VND, and is expected to be a key traffic axis connecting Nam Tu Liem district and Ha Dong district (Hanoi). |
Currently, there are 3 main contractors on the entire route, machinery, equipment and personnel are highly concentrated by the contractors. Currently, the unit only has the last section of the route bordering Ha Dong, the remaining volume is insignificant, ensuring the proposed progress. |
Once put into use, this route will help shorten travel time between Nam Tu Liem and Ha Dong districts, reducing traffic pressure on many routes in Hanoi. |
The investment project to build the extended Le Quang Dao route starts at the intersection with Thang Long Avenue (Nam Tu Liem District) and ends at Duong Noi urban area (Ha Dong District). |
Source: https://tienphong.vn/duong-le-quang-dao-keo-dai-lo-hen-du-kien-van-hanh-trong-thang-12-post1685468.tpo