Key transport projects must be completed before the Provincial Party Congress.

Việt NamViệt Nam08/02/2025


1.jpg
Provincial Party Secretary Luong Nguyen Minh Triet listens to the investor's representative report on the progress of the road connecting Vo Chi Cong Street in Thang Binh District. Photo: PHAN VINH

At the project of connecting Vo Chi Cong road to Dong Que Son Industrial Park connecting with National Highway 14H and National Highway 1, part of the project to complete coastal road 129 (Vo Chi Cong road), the Provincial Traffic Construction Investment Project Management Board said that the project implementation location is in Thang Binh and Duy Xuyen districts.

Component project 2 consists of 2 routes. Branch route 1: Road connecting Vo Chi Cong Street to Dong Que Son Industrial Park connecting to National Highway 14H with a length of about 19.4km, investing in 1/2 of the planned cross-section of 38m. Branch route 2: Road connecting Vo Chi Cong Street to National Highway 1 with a length of about 4km, investing in a cross-section suitable for the planning with a width of 38m = 2x10.25m road surface + 2.5m median strip + 2x7.5m sidewalk.

2(1).jpg
The Provincial Party Secretary directed units and localities to urgently complete the project items connecting Vo Chi Cong Street. Photo: PHAN VINH

For Component 2, localities have handed over 12km/23.1km. Of which, Thang Binh district is organizing exploitation to hand over the land of a 6.1km long forest land section; the remaining 4.5km due to the impact of national defense land, 0.3km is undergoing land recovery procedures, 1.2km of agricultural land has not been handed over, and 3km of residential land and housing must be cleared and resettled.

"However, the biggest problem in site clearance for Component 2 Project is the resettlement of 61 households whose residential land must be cleared (42 households in Thang Binh, 19 households in Duy Xuyen), the affected area is about 3.5km/23.1km" - Mr. Nguyen Van Thuong - Director of the Provincial Traffic Construction Investment Project Management Board said.

3.jpg
Many items of the Vo Chi Cong road connection project are behind schedule due to land acquisition problems. Photo: PHAN VINH

Therefore, to ensure the progress of the project, the Provincial Traffic Construction Investment Project Management Board requests the People's Committees of Thang Binh and Duy Xuyen districts to pay attention to directing the acceleration of the construction of resettlement areas to serve the project.

Of which, Thang Binh district has 4 areas including: New rural residential area in Hien Luong village, Binh Giang commune; New rural residential area in Ngoc Son Dong village, Binh Phuc commune; Ke Xuyen market residential area (phase 2) and Project to adjust the location of lot F/F1 out of the boundary of Ha Lam - Cho Duoc Industrial Cluster for resettlement. Duy Xuyen district has a new rural residential area in Nhon Boi village, Duy Thanh commune.

4.jpg
Provincial Party Secretary Luong Nguyen Minh Triet presents gifts to encourage the construction unit. Photo: PHAN VINH

Next, the delegation inspected the Van Ly Bridge Project and the approach road in Dai Loc district and Dien Ban town. The project has a total length of 7.78km, including a 3.65km branch connecting to DT609C and a 4.13km branch connecting to DT605. The project has a construction package worth more than 467 billion VND, a construction period of 900 days, to be completed before March 30, 2026. Currently, the bridge section is under construction.

6.jpg
Van Ly Bridge and approach road project completes construction of the bridge section. Photo: PHAN VINH

The entire 7.78km-long access road of the project has not yet been constructed. On January 22, 2025, Dai Loc district handed over 2km/3km of the land through Dai Hoa commune. In Dien Quang and Dien Hong communes (Dien Ban town), the compensation plan was only approved on January 23, 2025, and the land has not yet been handed over.

According to Mr. Nguyen Van Thuong - Director of the Provincial Traffic Construction Investment Project Management Board, the volume of land clearance for the approach road is still very large, only the site has been handed over in Dai Hoa commune, but the site is not continuous so the construction of the approach road cannot be organized yet. In addition, there are no resettlement areas to relocate the households cleared.

5.jpg
Provincial Party Secretary Luong Nguyen Minh Triet listened to the Provincial Traffic Construction Investment Project Management Board report on the progress of the Van Ly Bridge and Access Road Project. Photo: PHAN VINH

After inspecting each project and listening to the Provincial Traffic Construction Investment Project Management Board and localities report on the implementation status and difficulties, Provincial Party Secretary Luong Nguyen Minh Triet directed units to focus on removing and making efforts to handle difficulties.

In particular, focus on building resettlement areas, valuing land and related crops to quickly mobilize people to hand over land for the project. Departments and branches speed up the implementation of administrative procedures, especially the licensing of mines to have raw materials for investors to construct.

[VIDEO] - Provincial Party Secretary Luong Nguyen Minh Triet listened to Dai Loc district report on site clearance progress:

"For the project of the road connecting Vo Chi Cong Street to Dong Que Son Industrial Park connecting with National Highway 14H and National Highway 1, units must focus on completing it before the Provincial Party Congress. For the Van Ly Bridge and approach road project, the technical traffic progress must be completed before the Provincial Party Congress" - Provincial Party Secretary Luong Nguyen Minh Triet directed.

Comrade Luong Nguyen Minh Triet noted that these are key projects of the province in 2025, so departments, branches and localities should focus on implementing them flexibly in a spirit of urgency but must follow the correct procedures, regulations and laws.

7(1).jpg
Provincial Party Secretary Luong Nguyen Minh Triet presents gifts to the construction unit of Van Ly Bridge Project and access road. Photo: PHAN VINH


Source: https://baoquangnam.vn/bi-thu-tinh-uy-luong-nguyen-minh-triet-cac-du-an-giao-thong-trong-diem-phai-hoan-thanh-truoc-dai-hoi-dang-bo-tinh-3148677.html

Comment (0)

No data
No data

Same tag

Same category

Spectacular start of Vietnamese film market in 2025
Phan Dinh Tung releases new song before concert 'Anh trai vu ngan cong gai'
Hue National Tourism Year - 2025 with the theme "Hue - Ancient Capital - New Opportunities"
Army determined to practice parade 'most evenly, best, most beautiful'

Same author

Heritage

Figure

Business

No videos available

News

Political System

Local

Product