657,000 billion VND of public investment in 2024, mainly for transport infrastructure

Báo Tài nguyên Môi trườngBáo Tài nguyên Môi trường16/02/2024


657.000 tỷ đồng đầu tư công năm 2024, chủ yếu cho hạ tầng giao thông- Ảnh 1.

Prime Minister Pham Minh Chinh speaks at the 9th meeting of the State Steering Committee for important national projects and works, key to the transport sector - Photo: VGP/Nhat Bac

The meeting was held in a direct and online format between the Government Headquarters and 46 provinces and centrally-run cities with important national projects and key transport sector works and projects.

Attending the meeting were Deputy Prime Minister Tran Hong Ha, Deputy Head of the Steering Committee; members of the Steering Committee who are Ministers, Heads of ministerial-level agencies, Government agencies; Chairmen of People's Committees of provinces and cities; representatives of project management boards, state-owned economic groups, investors, consulting units, and construction contractors.

657.000 tỷ đồng đầu tư công năm 2024, chủ yếu cho hạ tầng giao thông- Ảnh 2.

The Prime Minister asked delegates attending the meeting to discuss and assess the situation and propose solutions to shorten the progress of works and projects, ensuring the quality and technical/aesthetics of the works - Photo: VGP/Nhat Bac

2024 is the year of acceleration

Opening the meeting, Prime Minister Pham Minh Chinh said that the whole country is promoting three growth drivers, including investment drivers, including domestic investment, foreign investment, private investment and social investment.

Emphasizing that public investment plays an important role in leading and activating all social resources for development investment, the Prime Minister said that in 2024, the whole country will spend 657,000 billion VND on public investment, mainly in transport infrastructure investment, and strive to achieve a disbursement rate of at least 95%.

Along with the effectiveness of promoting growth momentum, focusing on disbursing public investment, with transportation projects put into operation will contribute to reducing logistics costs for businesses, reducing input costs, increasing the competitiveness of products, businesses and the economy; creating new development space because wherever the road goes, it opens up new development space, especially industrial development, urban areas, services, etc.

"That affirms that the Party and State's determination to focus on implementing three strategic breakthroughs, especially infrastructure breakthroughs, especially transport infrastructure, is the right and wise choice, a decisive factor for immediate and long-term development," the Prime Minister affirmed. Each transport project has its own mission, functions and tasks, but in general, they are all very important and are strategic breakthroughs.

The Prime Minister said that in recent years, investment and development of transport infrastructure has been promoted, creating a movement and trend, "not only the Central but also the local level can do it". 2021-2022 is the stage of initiating, preparing and approving projects, 2023 will be implemented simultaneously, 2024 is identified as the year to accelerate the implementation of key transport projects.

Assessing 2023 as a successful year for infrastructure development - one of the three strategic breakthroughs, the Prime Minister commended the localities, ministries, branches, investors, contractors, consultants and people whose projects have passed through for their great efforts and synchronous implementation, especially with the working spirit of "through Tet, through holidays", "overcoming the sun, overcoming the rain", "working in 3 shifts, 4 shifts", "eating quickly, sleeping urgently", promoting the implementation of transport infrastructure works and projects, the more they work, the more mature they become in terms of thinking, awareness and action.

The Prime Minister also pointed out that the progress of some projects is still slow due to prolonged investment procedures; slow site clearance; lack of initiative in materials due to regulatory problems; policies and incentives for units and individuals to focus on promoting projects are not timely; relevant entities need to coordinate more closely and effectively...

The Prime Minister requested the delegates attending the meeting to discuss, assess the situation, propose solutions to shorten the progress of works and projects, ensure quality, technical/aesthetic works, ensure labor safety, hygiene, and environmental landscape. At the same time, remove difficulties and obstacles in using ODA capital, using sea sand to build traffic works...

657.000 tỷ đồng đầu tư công năm 2024, chủ yếu cho hạ tầng giao thông- Ảnh 3.

Leaders of the Ministry of Transport speak at the meeting - Photo: VGP/Nhat Bac

A successful year in implementing strategic breakthroughs in infrastructure

According to the report of the Ministry of Transport, in 2023, the Prime Minister chaired 05 Steering Committee meetings and together with Deputy Prime Ministers directly inspected the construction sites and projects; directed and issued many directives, telegrams, and documents to remove difficulties and obstacles, and urged ministries, branches, and localities to implement tasks.

In the early days of 2024, the Prime Minister issued two dispatches directing agencies and units to continue to promote the highest sense of responsibility, speed up the implementation of traffic infrastructure projects and works, and focus on removing difficulties and obstacles related to construction norms and unit prices; exploitation and supply of construction materials.

On the 3rd and 4th days of the Lunar New Year, Prime Minister and Deputy Prime Minister Tran Hong Ha inspected and extended New Year greetings at 5 key transport projects in Hanoi, Ho Chi Minh City, Dong Nai and Ba Ria-Vung Tau provinces to promptly direct, remove difficulties and obstacles, and encourage workers.

657.000 tỷ đồng đầu tư công năm 2024, chủ yếu cho hạ tầng giao thông- Ảnh 4.

Delegates attending the meeting - Photo: VGP/Nhat Bac

With the close and drastic direction of the Prime Minister and Deputy Prime Ministers, along with the close and responsible coordination and implementation efforts of ministries, branches and localities, many difficulties and problems that have existed for a long time in a number of projects have been focused on and resolved; investment preparation for projects has been accelerated, many projects have started construction in 2023; many projects have been inaugurated and put into use, promoting investment efficiency.

For newly implemented projects, most of them achieved or exceeded the set plan; the disbursement results of the projects were at a high level or exceeded the requirements. The Ministries of Planning and Investment, Natural Resources and Environment, Construction, and Finance have completed many tasks assigned by the Prime Minister.

Currently, the country has 34 major projects, 86 important national component projects, key transport sector projects in 46 provinces and centrally-run cities. Of these, there are 5 railway projects, 2 airport projects, the rest are road projects, mainly expressways and belt roads in the Hanoi capital region, belt roads in Ho Chi Minh City.

The North-South Eastern Expressway Project has completed 9/11 component projects in the 2017-2020 period and the My Thuan-Can Tho project as planned, bringing the total length of expressway to 1,892 km, of which 475 km will be completed in 2023; the remaining 2 projects are invested in the form of BOT contracts, investors and contractors are actively implementing to complete in accordance with the Prime Minister's direction.

For the 12 component projects in the 2021-2025 period, although there were many problems with construction sites and materials in the first year of implementation, investors and contractors have made efforts to organize construction and closely follow the set schedule.

For the 5 East-West expressway and beltway projects, the implementation progress is still slow, except for some packages managed by Ho Chi Minh City and Long An (Ring Road 3), Hanoi (Ring Road 4), Ba Ria-Vung Tau (Bien Hoa-Vung Tau expressway), Dak Lak and Khanh Hoa (Khanh Hoa-Buon Ma Thuot), which basically meet the plan.

Other expressway projects such as Tuyen Quang-Ha Giang section through Ha Giang province; Cao Lanh-An Huu; Ben Luc-Long Thanh are being implemented by investors and contractors closely following the set schedule.

The Nhon-Hanoi Railway Station urban railway project and the Ben Thanh-Suoi Tien project are being reviewed by Hanoi and Ho Chi Minh City, removing contractual obstacles, training personnel, completing fire prevention and fighting procedures, project acceptance, and system safety certification to strive to operate the Nhon-Hanoi Railway Station section and the Ben Thanh-Suoi Tien project in July 2024.

For the Long Thanh International Airport project, the packages under construction such as package 5.10 Passenger Terminal, the package for construction of works serving air traffic management have been directed by Vietnam Airports Corporation (ACV), Vietnam Air Traffic Management Corporation (VATM) to actively implement and closely follow the progress. The packages that have not yet started construction under component project 1 to build headquarters of state management agencies, component project 4 to build essential works are being implemented by the competent authorities for investment procedures; selecting investors. The package for Passenger Terminal T3 of Tan Son Nhat International Airport has been implemented by ACV, closely following the set progress, to date the disbursement has reached 2,477/10,825 billion VND (23%)...

The Electronic Information Portal continues to update information about the Meeting./.



Source

Comment (0)

No data
No data

Same tag

Same category

Overseas Vietnamese player Le Khac Viktor attracts attention in Vietnam U22 team
The creations in the TV series 'Remake' left an impression on Vietnamese audiences
Ta Ma - a magical flower stream in the mountains and forests before the festival opening day
Welcoming the sunshine in Duong Lam ancient village

Same author

Heritage

Figure

Business

No videos available

News

Ministry - Branch

Local

Product