DNO - Inspecting the Hoa Lien - Tuy Loan Expressway project on November 16, Deputy Minister of Transport Nguyen Danh Huy said that the contractor mobilized construction machinery that did not meet requirements, and many places had land but no machinery or equipment.
Also attending the inspection was Permanent Vice Chairman of the City People's Committee Ho Ky Minh.
Chairman of Hoa Vang District People's Committee Phan Van Ton reports on the site clearance situation. Photo: GIA MINH |
Reporting to the Deputy Minister, the representative of the Ho Chi Minh Road Project Management Board (HCM - the project investor) said that up to now, Hoa Vang district has handed over 11.27/11.47km of land to the project and there are still 2 locations of 220kV power lines. The total disbursement of the project to date is more than 340 billion VND (40%). In 2024 alone, nearly 270 billion (more than 70%) will be disbursed.
The Ho Chi Minh Road Project Management Board recommends that the locality accelerate the completion of legal documents, approval and payment of site clearance fees, and encourage households not to obstruct construction. At the same time, work with the electricity sector's management unit to resolve and arrange a power outage schedule to complete the relocation of high-voltage power lines in November 2024.
According to Mr. Ta Gia Manh Hung, Executive Director of the Hoa Lien - Tuy Loan Expressway Project, the project is currently lacking stone materials. In 2024, Da Nang will no longer have stone reserves to supply the project, and contractors will have to get them from other localities.
In the coming time, good weather will require the contractor to add machinery to speed up construction progress, ensuring the project is completed by August 2025 as directed by the Prime Minister.
Standing Vice Chairman of the City People's Committee Ho Ky Minh requested Hoa Vang district to thoroughly handle households with land issues. Contractors need to make a construction plan so that the local authorities can coordinate and support.
According to the Vice Chairman, Power Transmission Company 2 has planned to cut off power to relocate the high voltage power line on the route, and the parties are coordinating to implement this.
At the same time, the investor and contractor are requested to ensure traffic safety on the route so that people can travel smoothly during the upcoming Tet holiday.
Speaking at the meeting, Deputy Minister Nguyen Danh Huy commented that the current results of site clearance work are a great effort of the locality.
Current construction status of Hoa Lien - Tuy Loan expressway. Photo: GIA MINH |
According to the Deputy Minister, to ensure the project progress according to the Prime Minister's direction, the local authorities are requested to support construction at locations where the land has been handed over. The Ho Chi Minh Road Project Management Board will develop a specific construction plan and send it to the local authorities.
The Deputy Minister also requested the investor to meet with the construction contractor to detail the progress, and immediately supplement any areas where there is a site but no construction team. He requested the contractor to arrange at least 5 foundation construction teams for the project.
The Hoa Lien - Tuy Loan expressway section is 11.47km long, passing through 3 communes of Hoa Lien, Hoa Son, Hoa Nhon of Hoa Vang district.
In the phased phase, the project is invested with a scale of 4 complete lanes, roadbed width of 22m, road surface width of 14m, design speed of 80km/hour.
In the completed phase, the project will have a scale of 6 lanes, a roadbed width of 29m. The total investment is more than 2,100 billion VND. According to the plan, the project will be completed in 2025.
The project has 11 bridges, 8 underpasses, 62 culverts of various types and a service road on both sides of the highway over 20km long.
The project is invested by the HCM Road Project Management Board, and the supervising consultant is the Road Engineering Center 3.
The construction contractor is a joint venture of Truong Son Construction Corporation - CTGT 5 Construction Corporation - JSC and 17 LLC.
GIA MINH