On July 13, a representative of the Ho Chi Minh City Public Transport Management Center said that they are implementing a construction package under the project to increase accessibility and organize bus routes to metro stations No. 1 (Ben Thanh - Suoi Tien).
The contractor is simultaneously constructing 5 parking lots with a total area of 5,472m² next to Van Thanh, Thao Dien, Rach Chiec, Phuoc Long, Binh Thai stations. In addition, there are 67 bus shelters, 196 bus stops at 11 locations near metro stations and along both sides of the bus network routes connecting to metro line 1.
According to Giao thong Newspaper reporters, at Rach Chiec station area (Thu Duc city), the contractor is rolling and compacting the concrete base and pillars. Meanwhile, Van Thanh station parking lot has been paved with asphalt and has installed protective fences.
Construction area of the parking lot opposite Rach Chiec station (Thu Duc city). Metro passengers will park their motorbikes here to go up the pedestrian bridge connecting to the station.
Mr. Vo Duc Hung, supervising engineer of the Hong An - Saigon Traffic Joint Venture, said that the contractor has mobilized 70 workers and nearly 20 motorbikes to continuously construct to meet the progress required by the investor. The entire project has reached more than 60% of the total volume. The current advantage is that the contractor has been handed over the entire site. On days when there is unfavorable heavy rain, the contractor will work overtime the next night to make up for the progress.
A representative of the Ho Chi Minh City Public Transport Management Center said that the parking lots at Thao Dien and Binh Thai stations are currently more than 65% complete, while Rach Chiec and Phuoc Long stations are more than 50%. The parking lot at Van Thanh station is basically complete. It is expected that all items will be completed in August.
Along with parking lots, the city also built new parking lots for public vehicles with a total area of about 3,260 m² at 2 locations near Van Thanh Park Station and Binh Thai.
The project to enhance accessibility and organize connections between bus routes and metro station No. 1 has a total investment of VND92 billion from the city budget. When completed, these items will help people access the stations conveniently.
Metro Line 1 is the first urban railway line in Ho Chi Minh City with a total length of 19.7km, including 2.6km underground and 17.1km above ground. The project is currently 98% complete and aims to be commercially operational in the fourth quarter of this year.
Some images recorded by Giao thong Newspaper reporters along metro line 1:
At the construction site of the parking lot connecting to Thao Dien station, the contractor has completed the rough construction of the office. It is expected that in about 2 weeks, the fence and asphalt floor will be completed.
Perspective of the design of the parking lot under the pedestrian bridge connecting to Rach Chiec station. Bus stops are also located near the foot of the pedestrian bridge to ensure convenience for passengers.
The contractor has mobilized 70 workers and many motorbikes and equipment to speed up construction, aiming to complete the project in August 2024.
The location of Van Thanh station parking lot under the metro rail has been paved with asphalt, preparing to install the roof structure and electrical equipment.
The parking area under the pedestrian bridge connecting to Phuoc Long station. Here, the office and restrooms have been built in the rough. The contractor is installing drainage before grading the ground.
Along metro line 1, 67 bus stops and 196 bus stops will also be installed to enhance connectivity to stations.
With a parking system along the route, combined with pedestrian bridges and bus stations, Ho Chi Minh City hopes to fundamentally resolve congestion on routes from the central area to the eastern gateway and vice versa. (In the photo: Metro No. 1 trains are gathered at Long Binh Depot awaiting commercial operation at the end of this year - Photo: QT).