TPO - After more than a year of construction and taking advantage of long holidays to speed up the project's progress, the underpass for motor vehicles on Ring Road 2.5 passing through the Giai Phong - Kim Dong intersection has now taken shape.
After completing the site clearance, over the past year, the project implementation units have started digging both the open and closed tunnels. In Dinh Cong ward, the tunnel has taken shape. |
At Dinh Cong, construction units have completed 9 open tunnel sections and 1 closed tunnel section (the underground tunnel section runs through the railway and Giai Phong street). |
After pouring the tunnel segments and retaining walls, the tunnel cross-section width on each side is 2 mixed traffic lanes. |
At the project site on the morning of February 27, Mr. Do Duc Hung, representative of the investor, the Hanoi Traffic Construction Investment Project Management Board, said that after completing 9 open tunnel segments and 1 closed tunnel segment on the Dinh Cong side, contractors are currently constructing drainage ditches along both sides. |
Regarding the current status of the project construction at Dinh Cong, Mr. Ho Duc Phuc (Cienco4 Corporation - main contractor) managing the project said that the construction of the tunnel at Dinh Cong ward has been basically completed, however, the project here cannot continue to construct the road leading to the tunnel because there is a household that has built a temporary house and re-encroached (photo number 1), and a 630 KVA transformer station (photo number 2). |
With the project on Kim Dong Street (Giap Bat Ward, Hoang Mai District), the site is being expanded to construct a tunnel under Giai Phong Street and an open tunnel, access road... |
The Giai Phong - Kim Dong intersection is being divided by a median strip to expand the intersection. |
After the intersection expansion is completed, all vehicles traveling on Giai Phong Street will enter the temporary road towards Kim Dong, which has just been expanded. The intersection will be fenced off for drilling and digging the main tunnel. |
It is expected that from May 2024, the drilling and tunneling across Giai Phong Street to connect Ring Road 2.5 to Kim Dong Street will be carried out by construction units. |
The Ring Road 2.5 underpass project through Giai Phong Street has a total length of 460 meters, a scale of 4 lanes for motor vehicles and goes underground through the Giai Phong - Kim Dong intersection. The project started on October 6, 2022 with an investment of 778 billion VND, completed in the first quarter of 2025 with the goal of completing the Ring Road 2.5 route, reducing congestion at the Giai Phong - Kim Dong intersection.
At the project site on February 27, Mr. Do Duc Hung, Supervision Department 5, Hanoi City Traffic Construction Investment Project Management Board (investor) said that the project is still on schedule to open to traffic in the second quarter of 2025.