Cienco4 Group was selected as the construction contractor for the investment project to complete the construction according to the planning of N1 and D1 routes of Nam Cao University Area, Ha Nam province.
Tomorrow (March 20), Ha Nam province and Cienco4 Group will hold the Groundbreaking Ceremony of Package No. 11: Construction and installation of the investment project to complete the construction according to the planning of N1 and D1 routes of Nam Cao University Area, Ha Nam province.
End point of route N1 Nam Cao University, Ha Nam province.
Previously, on March 13, the Nam Cao University Management Board issued a notice approving the results of contractor selection for package No. 11.
The selected contractor is Cienco4 Group. The winning bid price is over 433 billion VND. The contract implementation period is 660 days.
The scope of package 11 of the investment project to complete the construction according to the planning of N1 and D1 routes of Nam Cao University Area includes construction of the route, completion of synchronous technical infrastructure such as: sidewalks, drainage, isolated trees; lighting; ensuring traffic safety.
Of which, route N1 is over 2km long. The starting point intersects with National Highway 1 in Hoang Dong ward, Duy Tien, Ha Nam. The ending point intersects with Cau Gie - Ninh Binh expressway, Tien Noi ward, Duy Tien, Ha Nam.
Route N1 is invested with a cross-section of 42m wide including: 4-lane main road for motor vehicles, 2 mixed lanes 21m wide; 9m wide median strip, 6m wide sidewalk on each side.
Route D1 is over 4km long. The starting point intersects with Route N1, in Tien Noi Ward, Duy Tien, Ha Nam. The ending point intersects with Ring Road 5, in Tien Hiep Commune, Duy Tien, Ha Nam.
Route D1 is invested with a cross-section of 68m wide, including: 8-lane main road, 15m wide on each side, 14m wide median strip, 12m wide sidewalk on each side.
Cienco4 Group is considered one of the largest transportation enterprises in Vietnam, possessing full technology and the capacity to construct most types of current transportation projects.
Before winning the bid to construct the investment project to complete the planning of N1, D1 routes of Nam Cao University Area, Cienco4 was "chosen" by investors in many key projects such as: North - South expressway sections Bung - Van Ninh; Hau Giang - Ca Mau; Khanh Hoa - Buon Ma Thuot expressway; Ring Road 4 of Hanoi Capital Region; Ring Road 3 of Ho Chi Minh City...
With the advantage of technology and experience, Cienco4 is also a contractor participating in the construction of aviation infrastructure at many major airports across the country such as: Long Thanh, Tan Son Nhat, Noi Bai, Cat Bi, Phu Bai.
Source: https://www.baogiaothong.vn/cienco4-trung-thau-hon-433-ty-dong-thi-cong-xay-dung-duong-ket-noi-dai-hoc-nam-cao-192250319154401633.htm