Mobilizing more than 800 skilled workers to erect poles and pull wires for Quang Trach Circuit 3 Project

Báo Đầu tưBáo Đầu tư26/05/2024


Mobilizing more than 800 skilled workers to erect poles and pull wires for the Quang Trach - Pho Noi Circuit 3 Project

EVNNPT has mobilized more than 800 skilled engineers and workers to participate in erecting poles and pulling wires for the project with the determination to complete the energization of this national key project in accordance with the Prime Minister's direction.

According to the report of Vietnam Electricity Group (EVN), the weather is currently in the transitional season, so rain, sunshine, and thunderstorms are erratic, causing difficulties for the construction of the 500 kV line project, circuit 3, Quang Trach - Pho Noi.

However, ministries, localities, EVN, and the National Power Transmission Corporation (EVNNPT) are working with contractors to make efforts to overcome disadvantages and are determined to complete projects according to the schedule assigned by the Prime Minister.

Up to now, 1,177/1,177 column foundation positions (100%) have been handed over, and 478/513 anchorage corridors (93%) have been handed over.

Engineers and workers of Power Transmission Company 1 participate in erecting pole position 17 of the 500kV Nam Dinh I - Thanh Hoa power line project.

With 35/513 corridors of anchored routes not yet handed over, only Quang Binh and Ninh Binh have completed the handover of corridor routes.

Seven provinces have not completed handing over the route corridor: Ha Tinh (9/113 remaining anchorages), Nghe An (3/87 remaining), Thanh Hoa (1/137 remaining), Nam Dinh (7/54 remaining), Thai Binh (5/46 remaining), Hai Duong (1/28 remaining) and Hung Yen (9/26 remaining).

Regarding the supply of steel columns, contractors have handed over 667/1,177 column positions. To speed up the production and handover of the remaining steel columns, the Investor has taken many solutions and resolutely directed and urged contractors.

Specifically, urge contractors to import enough input materials, install and optimize production lines, increase human resources and perform "3 shifts, 4 shifts, 24/7" processing. For contractors found to be behind schedule, EVN/EVNNPT and Project Management Boards require contractors to add more capable subcontractors to speed up progress.

Engineers and workers of Power Transmission Company 2 participate in erecting pole position 135 of the 500kV Quynh Luu - Thanh Hoa transmission line project.

The investor has also transferred different types of columns between construction packages to synchronize the supply of columns to completed foundation locations to minimize the waiting for columns and vice versa; speed up the acceptance and payment progress for contractors so that contractors have funds to continue purchasing materials and processing and manufacturing steel columns.

For overloaded and behind schedule contractors, the solution is to add more capable subcontractors to speed up the production and supply of columns. For imported steel column packages, we have worked with manufacturing partners to increase production, speed up the production and delivery before May 30, 2024.

During the construction, 1,162/1,177 foundations have been completed and 15/1,177 are under construction. 398/1,177 column installations have been completed and 222/1,177 column installations are under construction. 10/513 anchorage spans have been pulled and 7/513 anchorage spans are being pulled.

In which, the 500 kV Nam Dinh I - Thanh Hoa Power Line Project has completed casting the foundations of all 180/180 positions. Completed erection of 141/180 pole positions, and is currently erecting 33/180 pole positions. Completed pulling the wires of 4/74 anchor intervals, and is currently pulling the wires of 5/74 anchor intervals.

At the 500 kV Nam Dinh I - Pho Noi Power Plant Transmission Line Project, the foundation casting has been completed at 329/334 locations, and 5/334 locations are under construction. The erection of 113/334 pole locations has been completed, and 64/334 pole locations are under construction.

At the Quynh Luu - Thanh Hoa 500 kV Transmission Line Project, 198/200 foundations have been completed and 2/200 are under construction. 28/200 pole positions have been completed and 55/200 pole positions are under construction.

At the Quang Trach - Quynh Luu 500 kV Transmission Line Project, the foundation casting has been completed at 455/463 locations, and 8/463 locations are under construction at the same time. The erection of 116/463 pole locations has been completed, and 70/463 pole locations are being erected. The wire pulling of 6/197 anchor intervals has been completed, and the wire pulling of 2/197 anchor intervals is being carried out.

Engineers and workers of Power Transmission Company 4 participated in erecting pole position 190A of the 500kV Nam Dinh I - Pho Noi power line project.

According to EVN, to complete the project's energization according to the schedule assigned by the Prime Minister, EVN/EVNNPT is urgently urging construction contractors to focus on human resources and construction machinery to soon complete the construction of the pole foundation, pole erection, and wire stretching according to the committed schedule.

Urge contractors to supply equipment and materials (steel poles, conductors, porcelain, accessories, fiber optic cables, etc.) to promptly complete fabrication and transport to the construction site for installation.

The next planned implementation plan of all 4 current projects is to complete foundation casting on May 23, 2024 (in particular, Nam Dinh I - Thanh Hoa Project completed foundation casting on May 16, 2024); complete pole erection on June 15, 2024; complete insulation, accessory and wiring installation on June 20, 2024 and conduct testing, acceptance, and energization from June 20-30, 2024.

To ensure the progress of the 500kV line project, circuit 3, Quang Trach - Pho Noi, to be completed in June 2024, EVNNPT has mobilized skilled human resources from power transmission companies across the country to participate in erecting poles and pulling wires.

In the pole erection and wire pulling packages of the 500kV line 3 project, EVNNPT has mobilized an additional 800 skilled workers from power transmission companies in all 3 regions to support the acceleration of construction progress, bringing the project to the finish line as committed.

Power Transmission Company 4, the unit managing and operating the transmission grid in the Southern region, has "supported" the project by mobilizing 150 skilled engineers and workers to participate in erecting poles and pulling wires. Power Transmission Company 3, the unit managing and operating the transmission grid in the South Central and Central Highlands regions, has also increased 150 engineers and workers from power transmission lines to participate in erecting poles and pulling wires for the project. Power Transmission Company 2 has increased 120 workers. Power Transmission Company 1 has increased nearly 400 skilled engineers and workers to participate in erecting poles and pulling wires.

Mr. Nguyen Ba Dung, Deputy Director of Quang Ngai Power Transmission under Power Transmission Company 2, said that immediately after receiving the request from EVNNPT, the National Power Transmission Company 2 increased about 120 engineers and skilled workers, established 5 construction teams to erect poles and pull wires to support construction contractors.

Mr. Huynh Quang Thinh, Head of Technical Department, Power Transmission Company 3 said, for each assigned pole erection location, in favorable weather conditions, we will deploy construction from 15 to 20 days to complete a pole location with a pole erection volume of about 100 tons. Each engineer and worker participating in the Project has the highest determination to complete the pole erection work synchronously with other units.

Referring to the mobilization of additional forces and increased support for construction contractors to speed up the progress of erecting poles and pulling wires, Mr. Truong Huu Thanh, Deputy General Director of EVNNPT, said that EVNNPT has mobilized about 800 technical workers who know how to climb high and erect poles. In addition, implementing the Prime Minister's direction, EVNNPT has contacted other units such as Electricity Corporations, Oil and Gas Power Corporation, Viettel Group and VNPT Group to be ready to mobilize a very large force to participate in supporting the construction of pole erection and wire pulling packages.



Source: https://baodautu.vn/huy-dong-hon-800-nhan-luc-co-tay-nghe-de-dung-cot-keo-day-du-an-mach-3-quang-trach---pho-noi-d215993.html

Comment (0)

No data
No data

Same tag

Same category

Developing community tourism in Ha Giang: When endogenous culture acts as an economic "lever"
French father brings daughter back to Vietnam to find mother: Unbelievable DNA results after 1 day
Can Tho in my eyes
17-second video of Mang Den so beautiful that netizens suspect it was edited

Same author

Image

Heritage

Figure

Business

No videos available

News

Ministry - Branch

Local

Product