The Ministry of Transport has just issued a telegram on urgently completing construction items of the Dien Bien Airport expansion investment project to serve the operation.

According to the Ministry of Transport, the project to invest in the construction and expansion of Dien Bien Airport is being focused on by the project management board and contractors to complete and put back into operation from December 2.

The time left for Dien Bien airport to resume operations is very short, but the amount of work remaining at the construction site is still large.

Therefore, to ensure the quality of the project and the progress of putting it into operation, the leaders of the Ministry of Transport requested the Vietnam Airports Corporation (ACV) to direct the Project Management Board and contractors to focus all resources, equipment, people... to urgently complete all remaining work before November 26, ensuring quality.

At the same time, organize acceptance immediately after completing the construction of the remaining construction items according to regulations, promptly send all documents, acceptance minutes... to the Department of Construction Investment Management before November 27 for inspection, review, and approval of the results of the acceptance of completed works according to regulations. From there, it will be the basis for the Civil Aviation Authority of Vietnam to grant licenses for operation to ensure progress.

Event - Completing the final tasks to exploit Dien Bien airport from December 2

Dien Bien Airport expansion investment project with total investment of more than 1,400 billion VND.

Vietnam Air Traffic Management Corporation (VATM) is responsible for directing the Northern Air Traffic Management Company and contractors to urgently complete the construction of the AWOS automatic meteorological monitoring system and the remaining work on schedule, coordinate with ACV in digging cable trenches on the leveling strips and complete before November 26.

The Civil Aviation Authority of Vietnam and the Department of Construction Investment Management closely monitor the construction site, promptly resolve tasks within their authority, and promptly report to the Ministry of Transport any difficulties or problems with matters beyond their authority or progress at the construction site that is not guaranteed according to plan.

Dien Bien Airport expansion investment project with a total investment of over 1,400 billion VND. The project builds a runway measuring 2,400mx45m, a 2-way turntable, and a cement concrete structure to ensure the operation of Airbus A320/A321 aircraft or equivalent.

The passenger terminal is designed with 2 floors with modern architectural lines. In which, the first floor includes the lobby roof area, the departure passenger area and the arrival passenger area; the second floor is the waiting area, business class lounge, commercial services and auxiliary areas serving exploitation, the capacity of phase 1 is from 500,000 to 1 million passengers/year.

After Dien Bien Airport is upgraded and expanded, it is expected to contribute to attracting businesses to invest in the fields of tourism, trade, and services development, promoting the unique cultural values ​​of ethnic minorities, especially promoting the value of the Dien Bien Phu battlefield relic complex .



Source

Comment (0)

No data
No data

Same tag

Same category

Increasing Hanoi's attractiveness from flower tourism spots
International Music Festival 'Road To 8Wonder - The next icon'
Spectacular start of Vietnamese film market in 2025
Phan Dinh Tung releases new song before concert 'Anh trai vu ngan cong gai'

Same author

Heritage

Figure

Business

No videos available

News

Political System

Local

Product