TPO - The project to preserve, restore, and promote the value of Hai Van Quan relic has been adjusted to the end of the second quarter of 2024. Currently, the relic site is entangled with a 22kV power line that has not been buried underground and relocated, so some items cannot be constructed yet.
According to the plan, the project to preserve, restore, and promote the value of Hai Van relic will be completed and welcome visitors by the end of 2023. However, up to now, the special National Monument on the top of Hai Van Pass, bordering Da Nang City and Thua Thien-Hue Province, is still fenced off, prohibiting "unauthorized persons" from entering. Visitors to the top of Hai Van Pass can only stand on the roadside and look inside the relic. |
According to the investigation, the project is behind schedule partly because the power line of the Hai Van Pass transformer station that carries electricity to the radio station's transmitter and receiver station on the top of Hai Van Pass has not been buried underground and relocated. This power line crosses National Highway 1A and passes by the Hai Van Quan relic site, which has been carrying electricity to the transmitter and receiver station above the relic site for decades. |
Currently, in the Hai Van Quan relic area, there are 3 electric poles with power lines that have not been buried underground, although the underground road system through National Highway 1A, through the relic area, has been completed. |
The slow relocation of the electric poles has left the construction projects unfinished. The relic restoration contractor said that 95% of the project has been completed. The contractor is currently speeding up the progress of the remaining projects to complete the project as soon as possible. |
The representative of the construction unit said that some items of the project could not be completed on schedule due to power line problems. Up to now, the related issues have been resolved. Lien Chieu District Electricity has also announced a power outage schedule so that the construction unit of the underground power line package of the project can carry out the remaining work. |
After burying the power lines, the electric poles in the Hai Van Quan relic site will be relocated and restored to their original state. |
A corner of the project is still messy and cannot be constructed because the power lines have not been buried underground and the power poles have not been relocated. |
Hai Van Quan was built at an altitude of 490 m above sea level, where the two peaks of Hai Van Son (east) and Ba Son (west) meet, belonging to the Bach Ma - Hai Van mountain range. The relic is located in Lang Co town, Phu Loc district, Thua Thien Hue province and Hoa Hiep Bac ward, Lien Chieu district, Da Nang city. About 90 km south of Hue city center, about 28 km north of Da Nang city center |
After a long period of Hai Van Quan being in a state of "no one cries for a common father", in April 2017, the leaders of the cultural sectors of Da Nang and Hue joined hands to restore it, when Hai Van Quan was recognized as a National Monument. In December 2021, the project to preserve, restore, restore and promote the value of the new Hai Van Quan relic was officially started with a total investment of more than 42 billion VND. The investment capital was contributed by the two localities. |
Recently, the People's Committee of Thua Thien Hue province has issued a decision to adjust the project to preserve, restore, and promote the value of Hai Van Quan relic with the completion time until the end of the second quarter of 2024. |
Thanh Khe District Electricity has announced a power cut in the Hai Van Quan pass area from 8:30 a.m. to 3:30 p.m. (March 7) so that the construction unit can proceed to bury the 22kV power line that is passing through the Hai Van Quan national relic. |
Meanwhile, the Department of Culture and Sports of Da Nang City said that it is actively coordinating with the Hue Monuments Conservation Center to speed up the project. Immediately after the medium-voltage power line running through the monument was buried underground, the two sides continued to coordinate to speed up some remaining items and at the same time held working sessions to discuss management, exploitation, tourism services, and economic development plans between the two localities. |
Source
Comment (0)