Kinhtedothi - The Government Office has just issued Notice No. 119/TB-VPCP concluding Deputy Prime Minister Nguyen Hoa Binh's review and removal of difficulties and obstacles related to key transport projects scheduled to be completed in 2025 to achieve the target of 3,000km of expressway.
The concluding announcement stated that the 13th National Party Congress set a target of completing 5,000km of expressways by 2030. The Prime Minister issued a Plan to implement the peak emulation campaign "500 days and nights of emulation to complete 3,000km of expressways" by 2025. This is the responsibility of all levels, sectors and the whole society in implementing the goals of developing transport infrastructure, creating achievements to welcome the 14th National Party Congress.
Given the importance of this task, the Prime Minister has decided to establish 7 Inspection Teams to review and remove difficulties and obstacles related to key transport projects scheduled to be completed by 2025 to achieve the target of 3,000km of expressway.
In recent times, localities have made great efforts in site clearance and implementation of assigned tasks; investors, consultants, contractors, engineers and especially workers have worked enthusiastically and tirelessly on construction sites to complete key projects.
Up to now, some of the implemented tasks have had specific results, contributing to solving the difficulties and obstacles of the project; however, there are still some tasks that need continued leadership, direction and resolution by the leaders of the provinces, ministries, branches and the efforts of investors, contractors, as well as the consensus and support of the people to be completed by the end of 2025.
Therefore, the Deputy Prime Minister requested localities, agencies and units to urgently and seriously implement key tasks to complete the goals of the emulation movement "500 days and nights of emulation to complete 3,000km of expressway" launched and directed by Prime Minister Pham Minh Chinh in Official Dispatch No. 673/TTg-CN dated September 5, 2024.
The Deputy Prime Minister requested the People's Committees of the provinces and cities of Da Nang, Quang Ngai, Binh Dinh, and Phu Yen to pay attention to and direct the resolution of difficulties and problems within their authority related to site clearance, relocation of technical infrastructure, material sources, construction material prices, as well as to strengthen the work of mobilizing and propagating people to create maximum conditions for the project.
For the People's Committee of Da Nang City, the Deputy Prime Minister requested to comply with the commitment at the meeting, complete all site clearance work in March 2025 and commit to starting construction of 1 resettlement area, completing procedures for the remaining 2 resettlement areas in March 2025, and completing all construction in June 2025 to ensure disbursement of all allocated capital.
Direct local authorities at all levels where the project passes through to strengthen propaganda, mobilize some households to accompany, share and support, create conditions for units to take advantage of good weather, be allowed to construct during breaks, ensure "3 shifts, 4 shifts" to complete the project on schedule.
Regarding the People's Committee of Quang Ngai province, the Deputy Prime Minister requested to direct and support the Quang Ngai - Hoai Nhon Expressway Project when there is an official proposal from Project Management Board 2 and the contractor to add 2 more quarries to the material supply dossier for the Project and to increase the annual exploitation capacity according to the special mechanism by 02 more quarries currently being exploited; direct the Investor, contractor and related units of the National Highway 1A - My A - Pho Phong Industrial Park Project to urgently resolve all existing problems and difficulties, mobilize all resources to focus on implementing the construction and completion of the entire National Highway 1A - My A - Pho Phong Industrial Park Project to ensure connection, operation and exploitation in sync with the Quang Ngai - Hoai Nhon Expressway Project.
For the People's Committee of Phu Yen province, in accordance with the commitment at the meeting, speed up the progress of site clearance for handover in March 2025; create conditions to increase the annual exploitation capacity of the stone quarry of Phu Yen Road Management and Repair Joint Stock Company to serve the demand for stone used to make asphalt concrete.
The Deputy Prime Minister assigned the Ministry of Finance to coordinate with the Ministry of Construction and the provinces and cities of Da Nang, Quang Ngai, Binh Dinh, and Phu Yen to review the capital sources of the 2025 Capital Allocation Plan and the 2026 Capital Plan to ensure sufficient funding for projects to be completed in 2025.
The Ministry of Construction focuses on directing investors, contractors and relevant agencies and units not to be negligent or subjective, to continue to proactively and actively implement and make more efforts, determined to complete the main expressway routes of 4 projects: Hoa Lien - Tuy Loan, Quang Ngai - Hoai Nhon, Hoai Nhon - Quy Nhon, Quy Nhon - Chi Thanh before September 30, 2025 (for tunnel No. 3 of the Quang Ngai - Hoai Nhon Project, it will be completed before December 31, 2025); complete rest stops and intelligent traffic management system (ITS), toll collection system (ETC), and vehicle load inspection in 2025.
The Ministry of Construction coordinates with relevant agencies to organize site inspections at least once a month and resolutely and strictly handle contractors who violate the contract in accordance with regulations; requires consulting units to closely monitor the site, strictly control the construction process, acceptance, quality control, speed up work progress and promptly handle design adjustments and additions (if any), absolutely not trading quality for progress.
The Deputy Prime Minister requested that Investors/Project Management Boards closely follow the site to promptly urge, direct, and operate the project, closely control the implementation progress; promptly remove difficulties and obstacles during the construction process according to their authority (especially for Subcontractors who are behind schedule, showing signs of slow construction) and periodically report to the Ministry of Construction before the 30th of each month or when difficulties/problems arise beyond their authority.
The coming time is the stage of mass construction of foundation and road surface items, requiring a huge amount of financial resources for implementation. It is recommended that the investor direct the acceleration of acceptance and payment procedures; have a mechanism to strictly control financial resources to avoid negativity and violations, and control daily and weekly construction progress, promptly have solutions to handle violating contractors to ensure project completion progress.
In addition, the investor is required to closely coordinate with local authorities, organize a review of the sewer, ditch, and access road systems to promptly supplement (if necessary); review the entire system of public roads borrowed from the locality, house vibration and cracks, and the impact of sedimentation and water erosion (if any) to direct the contractor to have a plan for repayment and compensation according to regulations, and complete it in parallel with the completion of the project. The Director of the Project Management Board is fully responsible for any delays or failure to complete the project according to the set schedule.
Require contractors to urgently increase human resources, equipment, proactively gather supplies, materials, financial resources, etc. to speed up the completion progress in accordance with the commitment and have a written commitment to complete the shortened progress sent to the investor and the Ministry of Construction for monitoring and urging; at the same time, study and supplement reasonable construction organization solutions during overtime construction at night to limit the impact on households in the area/scope of the Project implementation.