Appearance of the 2,000 billion VND bridge on the Huong River in the final construction phase, nearing the finish line

Báo Tiền PhongBáo Tiền Phong09/03/2025

TPO - Nguyen Hoang Bridge - a key traffic project across the Perfume River in Hue city, is currently entering the final construction phase to complete technical traffic in time for the 50th anniversary of Hue Liberation Day.


TPO - Nguyen Hoang Bridge - a key traffic project across the Perfume River in Hue city, is currently entering the final construction phase to complete technical traffic in time for the 50th anniversary of Hue Liberation Day.

Appearance of the 2,000 billion VND bridge on the Huong River in the final construction phase, nearing the finish line photo 1

The Nguyen Hoang road bridge project across the Huong River connecting Thuan Hoa and Phu Xuan districts (Hue City) will start construction in December 2022, with a total investment of more than VND 2,280 billion, invested by the Hue City Traffic Construction Investment Project Management Board.

Appearance of the 2,000 billion VND bridge on the Huong River in the final construction phase, nearing the finish line, photo 2

The bridge is about 380m long and 43m wide, including 6 lanes, a safety strip and a 3m wide sidewalk on both sides of the bridge. In particular, the bridge is designed with 4 curved branches, connecting to the park on both banks of the Huong River, creating an architectural highlight in harmony with the natural landscape of Hue.

Appearance of the 2,000 billion VND bridge on the Huong River in the 'final' construction phase, nearing the finish line photo 3

Nguyen Hoang Bridge and the connecting road system are expected to be completed within 3 years from the start of construction (December 2025). The project not only completes the connecting traffic infrastructure, but is also expected to create an important boost to promote the socio-economic and tourism development of the ancient capital.

Appearance of the 2,000 billion VND bridge on the Huong River in the final construction phase, nearing the finish line photo 4

Faced with the urgent need to expand the transport network, as well as to create a mark on investment in transport construction to welcome Hue becoming a centrally-run city, towards the 50th anniversary of Hue Liberation Day (March 26, 1975 - March 26, 2025), the local government has directed investors and contractors to focus all their efforts on speeding up the construction progress of the project.

Appearance of the 2,000 billion VND bridge on the Huong River in the final construction phase, nearing the finish line photo 5

During the construction process, the project faced many challenges, especially the harsh weather in the Central region, along with limiting the impact on the flow, ensuring the safety of waterways and the ecosystem of the Huong River. Currently, more than 190 engineers and workers are working day and night to ensure progress, with more than 97% of the project completed.

Appearance of the 2,000 billion VND bridge on the Huong River in the final construction phase, nearing the finish line photo 6

According to the plan, the asphalt paving of the bridge surface will be completed before March 15. Contractors continue to focus on completing the remaining items to ensure the technical traffic opening on March 26, on the occasion of the 50th anniversary of Hue Liberation.

Appearance of the 2,000 billion VND bridge on the Huong River in the final construction phase, nearing the finish line photo 7

In these final days of "sprinting", the construction atmosphere at Nguyen Hoang bridge site has become busier and more bustling than ever.

Appearance of the 2,000 billion VND bridge on the Huong River in the final construction phase, nearing the finish line photo 8

The new black asphalt surfaces give the building a solid and modern feel.

Appearance of the 2,000 billion VND bridge on the Huong River in the final construction phase, nearing the finish line photo 9Appearance of the 2,000 billion VND bridge on the Huong River in the final construction phase, nearing the finish line photo 10

Road rollers, asphalt pavers and many other construction equipment operate at full capacity, with the desire to ensure that every meter of road is of the best quality when put into use.

Appearance of the 2,000 billion VND bridge on the Huong River in the final construction phase, nearing the finish line photo 11

One of the highlights of Nguyen Hoang Bridge is the use of a special steel arch system when constructing the main structure of the project to increase durability and load-bearing capacity; both ensuring the quality of the project and minimizing construction time, helping to speed up the completion process.

Appearance of the 2,000 billion VND bridge on the Huong River in the final construction phase, nearing the finish line photo 12

A representative of the Nguyen Hoang bridge construction unit said that the project is now more than 97% complete. Of which, the difficult items of the project, the main structure of the bridge, have been basically completed. "To ensure the progress of the project, for more than 10 consecutive days, we have always worked until after 2 am before stopping. In addition, the unit always encourages and takes care of the workers wholeheartedly to ensure their health, work safely, and strive to complete the project on schedule," said a contractor representative.

Appearance of the 2,000 billion VND bridge on the Huong River in the final construction phase, nearing the finish line photo 13

Recently, the working group of the State Appraisal Department of Construction Quality had a working session with the leaders of Hue City People's Committee and the project investor. The representative of the working group noted that the conditions for the completion of the project should be ensured for early technical acceptance. The bridge inspection and load testing is expected to be completed on March 10. The remaining items will be completed before March 20, in time for technical acceptance on March 26.

How is the rotten 64 billion VND ironwood bridge in Hue being handled?
How is the rotten 64 billion VND ironwood bridge in Hue being handled?

Closing date for overpass worth over 2,200 billion VND across Huong River
Closing date for overpass worth over 2,200 billion VND across Huong River

Hue builds new bridge worth 75 billion VND to replace the construction where garbage truck crashed into river
Hue builds new bridge worth 75 billion VND to replace the construction where garbage truck crashed into river

The Nghia - Ngoc Van



Source: https://tienphong.vn/dien-mao-cau-2000-ty-tren-song-huong-giai-doan-thi-cong-nuoc-rut-sap-ve-dich-post1723317.tpo

Comment (0)

No data
No data

Same tag

Same category

Indonesia fired 7 cannon shots to welcome General Secretary To Lam and his wife.
Admire the state-of-the-art equipment and armored vehicles displayed by the Ministry of Public Security on the streets of Hanoi
“Tunnel: Sun in the Dark”: The first revolutionary film without state funding
Thousands of people in Ho Chi Minh City wait to take Metro Line 1 on its inauguration day.

Same author

Heritage

Figure

Business

No videos available

News

Ministry - Branch

Local

Product