Speed ​​up the construction of Children's Hospital

Báo Tiền PhongBáo Tiền Phong14/04/2024


TPO - Currently, the construction project of Hanoi Children's Hospital is in the process of completion. Of which, the construction and plastering work has reached about 95%, the tiling work has reached 15% and the mechanical and electrical system has reached about 35%.

Hanoi: Speeding up the construction progress of Children's Hospital 1

The Hanoi Children's Hospital construction project phase 1 includes a 6-storey main building, 1 basement with a total floor area of ​​approximately 34,364m2.

Hanoi: Speeding up the construction progress of Children's Hospital 2

Items in phase I include: Outpatient examination and treatment block; paraclinical technical block; administrative and logistics block according to hospital capacity scale and usage needs; inpatient treatment block (200 beds); procurement and installation of construction equipment for construction items.

Hanoi: Speeding up the construction progress of Children's Hospital 3

Up to now, the project has completed the rough part and is currently carrying out the finishing work. The project management board continues to urge related units to deploy construction and install equipment to complete the project to ensure safety, quality and progress.

Hanoi: Speeding up the construction progress of Children's Hospital 4

It is known that the project has registered to put up an inauguration sign to celebrate the 70th anniversary of the Liberation of the Capital (October 10, 1954 - October 10, 2024).

Hanoi: Speeding up the construction progress of Children's Hospital 5
At the meeting with the Project Management Board in early April 2024, Vice Chairman of the Hanoi People's Committee Vu Thu Ha requested relevant units to speed up the progress as much as possible. At the same time, the Hanoi Department of Health was assigned to review all contents related to the hospital's operating apparatus and begin research on phase 2 of the project.
Hanoi: Speeding up the construction progress of Children's Hospital 6

Currently, construction units are focusing on human resources to implement the project on schedule (Photo: Trong Tai).

Hanoi: Speeding up the construction progress of Children's Hospital 7

When the project is completed and put into operation, it will contribute to reducing the density and number of pediatric beds for general hospitals in Hanoi.

The project to build Hanoi Children's Hospital Phase 1 (Yen Nghia Ward, Ha Dong District, Hanoi) started at the end of February 2022. This is a Grade 1 Children's Hospital, established under Decision No. 1646/QD-UBND dated April 11, 2016 of Hanoi People's Committee.

According to the Hanoi City Civil Construction Investment Project Management Board, phase 1 includes a 6-storey main building and 1 basement with a total floor area of ​​approximately 34,364 square meters.

Up to now, the project has completed the rough part and is currently carrying out the finishing work. Specifically, the construction and plastering work has reached about 95%; the tiling work has reached about 15%; the mechanical and electrical systems have reached about 35%;

In addition, imported equipment includes medical equipment, elevators, low voltage electricity, indoor pumps, heat pumps, hot water tanks, and hot water systems. The remaining equipment has been ordered by the contractor and will be delivered according to the committed schedule.

It is expected that to ensure the operation of departments and rooms, the hospital's staff will be 109 people.

Thanh Hieu



Source

Comment (0)

No data
No data

Same tag

Same category

Explore Lo Go - Xa Mat National Park
Quang Nam - Tam Tien fish market in the South
Indonesia fired 7 cannon shots to welcome General Secretary To Lam and his wife.
Admire the state-of-the-art equipment and armored vehicles displayed by the Ministry of Public Security on the streets of Hanoi

Same author

Heritage

Figure

Business

No videos available

News

Ministry - Branch

Local

Product