On the morning of January 30, the Management Board of Traffic Construction Investment Projects of Da Nang City and the Management Board of Priority Infrastructure Investment Projects of Da Nang City inaugurated three key and vital traffic works.
In particular, the DT 601 road project is nearly 36 km long, starting at the intersection with DT 602 road, and ending at the border of Thua Thien - Hue.
The project started in May 2020, including 4 main packages with construction consortiums, represented by Construction and Trading Company No. 126, Lien Viet Tien Construction Joint Stock Company, One Member Company Limited 17, Tay Ninh Construction Investment Joint Stock Company.
Inauguration of 3 main roads
This is a key traffic project connecting the three communes of Hoa Son, Hoa Lien and Hoa Bac (Hoa Vang District), with the Da Nang Traffic Construction Investment Project Management Board as the investor and project manager, with a total investment of 725 billion VND.
The completed route helps improve, complete and connect traffic in rural communes of Hoa Vang district, develop socio-economy and national defense and security, and facilitate rescue during the flood season.
DH2 route started construction in October 2018 and was completed on June 30, 2022, constructed by Construction Service and Trade Joint Stock Company 68, nearly 9 km long, connecting National Highway 14G with Provincial Road 602, running parallel to the southern bypass of Hai Van - Tuy Loan tunnel.
Reward units that contribute to project completion
This is one of the main routes, connecting the residential areas in the north, south, and southwest with the district administrative center, especially connecting the city's traffic network with the Hoa Lien - Tuy Loan and Da Nang - Quang Ngai expressways, reducing traffic pressure on the Hai Van - Tuy Loan bypass.
Western Ring Road 2 (from Road No. 8, Hoa Khanh Industrial Park to Hai Van - Tuy Loan bypass) started construction in December 2019 and was completed on June 30, 2023, by a joint venture of Truong Son Construction Corporation - Dacinco Construction Investment Co., Ltd. - Cienco 4 Group Joint Stock Company - Nhat Huy Construction and Trading Co., Ltd.
The 4.6 km long route includes 4 main intersections, of which the last intersection is designed with a semi-asterisk-shaped level difference, 3 three-way and four-way intersections, and Quan Nam bridge over Hoa Lien flood drainage canal.
The routes put into operation help complete the transportation network.
The completion of this section of the route will help shorten the transportation of goods from Lien Chieu port to industrial parks, reduce the traffic of heavy trucks on Nguyen Luong Bang axis and the southern route of Hai Van tunnel.
Mr. Le Trung Chinh, Chairman of the People's Committee of Da Nang City, said that all three key traffic projects require huge land clearance and resettlement arrangements, with more than 2,500 households affected. Of which, Route 2 is the most affected with more than 1,200 households, Route 601 nearly 1,000 households and Western Belt Road 2 (phase 1) more than 330 households.
"Completing the site clearance was particularly difficult, going through complex and long mountainous terrain, unfavorable storms, Covid-19... but the units made great efforts and determination and received sympathy and sharing from the households. I sincerely thank the understanding of the households and units that were affected, inconvenienced, and had difficulties in traveling and doing business to construct the project, completing it before Tet to bring common benefits to the community", said Mr. Le Trung Chinh.