The Government has just issued a resolution agreeing on the mechanism and solutions to handle difficulties and obstacles in the investment project to build the second facility of Bach Mai Hospital and Viet Duc Friendship Hospital at the request of the Ministry of Health.
Bach Mai Hospital 2 (Phu Ly City, Ha Nam) is still under construction and has not been completed - Photo: NAM TRAN
The Government has just issued Resolution No. 34 on mechanisms and solutions to handle difficulties and obstacles in the investment project to build the second facility of Bach Mai Hospital and Viet Duc Friendship Hospital.
Accordingly, the Government agreed on the mechanism and solutions to handle difficulties and problems in the above two projects as proposed by the Ministry of Health.
Specifically, the goal is to propose practical, feasible solutions based on practice to promptly complete investment in construction and put into use the second facility of these two hospitals.
Principles for handling difficulties and problems are applied appropriately to current policies and laws, ensuring feasibility in implementation.
At the same time, continue to implement the investment according to the total investment approved by the competent authority. In case it is necessary to supplement funding to ensure the completion and synchronous operation of the two projects, the Ministry of Health shall preside over and coordinate with relevant agencies to report to the competent authority for consideration and decision.
The solution to the problem must be objective and honest, based on the current status of legal documents and related documents reported by the investor; the current status of the construction site and the results of inspection, examination and audit by competent authorities.
Regarding the mechanism and solution, the Government allows adjusting the contracts of the bidding packages XDBM-01, XDBM-02; XDVĐ-01, XDVĐ-02 to continue to complete the contracts on the following principles.
Firstly , the adjusted contract price is established according to the approved construction drawing design estimate after discounting the savings rate (%) when bidding for each bid package.
Second , the price adjustment of the contracts does not exceed the total approved investment of the project.
Third , the contract payment value is established on the basis of the actual completed volume that has been accepted and the detailed contract unit price is adjusted accordingly at the time of payment acceptance.
The value of payment for the contract volume does not exceed the adjusted contract price (excluding contingency). The contingency cost (if any) in the approved construction drawing design estimate is only used to pay for the increased volume (if any) compared to the volume in the approved construction drawing design.
The resolution takes effect from February 13.
The Government also assigned the Ministry of Health to direct the investor to urgently organize the implementation of contract adjustments and organize the implementation of the two projects according to the mechanisms and solutions stated in this resolution, ensuring the completion of construction this year.
At the same time, direct Bach Mai Hospital and Viet Duc Friendship Hospital to ensure human resources and other necessary conditions to effectively operate the second facility immediately after the two projects are completed and put into use.
The Ministry of Planning and Investment and the Ministry of Finance report to competent authorities to arrange additional capital for the two projects to ensure capital needs according to the implementation progress of the two projects and in accordance with regulations.
The Ministry of Construction continues to appraise the cost estimate for the technical design phase of the electromechanical items of the investment project to build the second facility of Bach Mai and Viet Duc Hospitals. According to the assigned functions, tasks and authority, promptly guide the Ministry of Health and direct relevant units to implement this resolution to ensure progress and quality.
The Ministry of National Defense, according to its assigned functions, tasks and authority, directs relevant units to implement this resolution to ensure progress and quality.
The Government also requested the State Audit to conduct an audit of the project completion settlement report according to regulations.
The Ministry of Health and relevant agencies, according to their assigned functions and tasks, are responsible for the contents, reported data, and mechanisms and solutions to handle difficulties and problems in the investment project to build the second facility of Bach Mai Hospital and the investment project to build the second facility of Viet Duc Friendship Hospital.
The hospital was built more than 10 years ago but has not yet been put into operation.
At the end of 2014, the second facility of Bach Mai and Viet Duc Hospitals in Phu Ly City (Ha Nam) began construction and is expected to be the two largest modern hospitals ever built. This is also the first time our country has a hospital built and operated according to international standards.
In October 2018, the examination areas of both facilities were officially inaugurated.
However, after that, only the examination area of Bach Mai Hospital was put into use for a period of time from March 2019 to March 2020 and then announced a temporary suspension of operations. Meanwhile, Viet Duc Hospital, branch 2, also only stopped at the ribbon cutting ceremony and never received patients.
The two hospitals have a scale of 1,000 beds/hospital; floor area of 100,000m²/hospital. Total investment is nearly 5,000 billion VND/hospital.
Source: https://tuoitre.vn/chinh-phu-go-kho-cho-hai-du-an-benh-vien-bach-mai-va-viet-duc-co-so-2-20250217105956149.htm