At the end of the first 6 months of 2024, Tien Yen district is the locality that has fulfilled its commitment and led the whole province in terms of public investment disbursement rate and continued to focus on solutions to speed up the progress of works and projects.

In 2024, Tien Yen district was assigned a total public investment capital plan of over 735 billion VND to implement 39 projects. Of which, 14 transitional projects and 25 newly started projects will be implemented. Public investment capital is mainly from the provincial budget to directly support the project, support according to scoring criteria, support the National Target Program on New Rural Development and support the overall socio-economic development program.
With a strong spirit in directing and reviewing progress every week to have solutions to remove obstacles and difficulties for each project, currently the transitional works ensure the volume and disbursement plan. For example, at the project to renovate and upgrade the headquarters of the District Party Committee, People's Council, and People's Committee - one of the key works of the district to improve the quality of service to the people and celebrate the 70th anniversary of Tien Yen Liberation Day. Although the construction volume is large, in less than a year of construction, the project has completed over 85% of the work volume; the disbursement volume reached more than 25/77 billion VND of the capital allocated to the project in 2024. Mr. Vu Trung Dung (chief construction supervision consultant) said: In order to strive to put the core project, a 10-storey building, into use before the beginning of August, the units organized 3 continuous shifts to complete the items. When the equipment is installed, the disbursement rate of capital allocated to the project will increase this July.

Along with the project to renovate and upgrade the headquarters of the District Party Committee, People's Council, and People's Committee, social security transition projects are allocated large capital sources in 2024, such as: Technical infrastructure improvement in the core area of Tien Yen town; embankment to prevent landslides and protect residential areas on the riverbank of Tien Lang commune; Dong Ngu I Primary School; upgrading and expanding the road from National Highway 18 to Pac Sui waterfall; upgrading and expanding the road from Dong Ngu commune to Dai Duc commune... are also ensuring construction progress and disbursing nearly 50% of the capital plan for the project in 2024.

With the strong direction of the District Party Committee, People's Council and People's Committee in the disbursement of public investment capital, by the end of the first 6 months of this year, Tien Yen district had disbursed nearly 310 billion VND, reaching 42.1% of the capital plan assigned at the beginning of the year. Of which, the provincial budget capital to support the implementation of the Overall Program for Socio-Economic Development in Ethnic Minority Areas reached nearly 46%; support for the implementation of the National Target Program on New Rural Construction reached over 47%; capital according to scoring criteria reached 51%; direct support capital for projects reached 40%.

Mr. Nguyen Te Hanh, Director of the Tien Yen District Construction Investment Project Management Board, said: Currently, the projects in the list of new construction plans in 2024 have completed the selection of contractors, signed contracts and started construction; continuing to promote the results achieved in the first 6 months of the year, the district resolutely directed units, departments and functional offices to strengthen coordination to remove difficulties, especially site clearance and land use conversion to ensure compliance with regulations, especially some newly started projects with large capital allocations. At the same time, construction units are required to take advantage of favorable weather conditions to increase human resources and equipment to speed up the construction progress of the works; strive to ensure that by the end of September, the disbursement rate of public investment capital reaches over 80% and complete 100% of the capital plan by the end of December this year.
Source
Comment (0)