
Inspecting the Viet An Industrial Park project, according to the report of Hiep Duc District People's Committee, the project area is 7.2 hectares; investing in a traffic route with a total length of 239m with a cross-section of 18.5m and a parking area, drainage system. The project implementation period is from 2022 - 2024 with a total investment of more than 29.9 billion VND.
The People's Committee of Hiep Duc district has approved the compensation, support and payment plan for site clearance for 23/39 households, with a total recovered land area of 1.3/7.14ha; 127 graves have been relocated. The remaining cases due to 5% of the land being not production forest land (7 households) and the case with 5% of the land being production forest land (12 households) are still waiting for instructions from the superior agency, so there is not enough basis to approve the plan.
The value of the project's construction volume is 0%. The accumulated capital allocated is 20 billion VND from the provincial budget; the accumulated disbursement to date is more than 8 billion VND (reaching 40.34%).

Mr. Nguyen Van Nam - Chairman of Hiep Duc District People's Committee said that the total public investment capital in 2024 in the district is more than 173.3 billion VND; of which the capital plan for 2024 is more than 130.2 billion VND, the capital plan for 2023 is extended and the source is transferred more than 43.1 billion VND.
The District People's Committee has allocated detailed capital investment plans for 2024 to sectors and localities of 118/130.2 billion VND (reaching 90% of the plan); the remaining unallocated capital is more than 12.2 billion VND. As of September 15, 71.8/173.3 billion VND (reaching 41.4%) has been disbursed. The total balance of advanced public investment capital as of September 15 is more than 56.9 billion VND.

“Currently, the capital disbursement rate is low compared to the direction of the Provincial People's Committee. The reason is that compensation and site clearance work is facing many difficulties, especially the confirmation of land origin is difficult due to the history of land management; the compensation price for houses, structures, crops, and livestock in some areas and locations is not close to reality; in some locations, people request investors to compensate too high compared to the general level.
Besides, the fluctuation in prices of raw materials and construction materials, the scarcity of common construction materials such as soil, sand, etc. have affected the construction progress and disbursement of projects," said Mr. Nam.
At the meeting, representatives of the Department of Natural Resources and Environment, Department of Planning and Investment, Department of Finance... analyzed the causes and proposed solutions to remove obstacles to speed up construction progress and disbursement of public-private capital in 2024 in Hiep Duc district.

Vice Chairman of the Provincial People's Committee Tran Nam Hung emphasized that disbursement is an important task, requiring the entire political system, the Fatherland Front, and local organizations to join in and carry out with high determination. At the same time, he requested the Standing Committee of Hiep Duc District Party Committee to continuously meet on the progress of disbursement of public investment capital; the Secretary of the District Party Committee directed the removal of each related part of the work and reported specifically to Working Group No. 3 of the province.
“The district’s working groups on accelerating the disbursement of public investment capital must closely follow reality, work with each sector and locality and actively direct implementation. Strive to have Hiep Duc’s public investment disbursement rate reach over 90% by the end of the year,” Mr. Hung requested.
[ VIDEO ] - Vice Chairman of the Provincial People's Committee Tran Nam Hung inspected the actual projects:
Vice Chairman of the Provincial People's Committee Tran Nam Hung also requested Hiep Duc district to proactively overcome the causes of weak contractor capacity and lack of human resources for land work. At the same time, speed up the progress of site clearance, proactively provide resettlement land funds and quarries of soil and sand for the projects.
Source: https://baoquangnam.vn/phan-dau-den-cuoi-nam-ty-le-giai-ngan-von-dau-tu-cong-cua-hiep-duc-dat-hon-90-3141267.html
Comment (0)