TPO - An Phu is the most important and largest traffic intersection in Ho Chi Minh City, construction started at the end of 2022. After more than 19 months of construction, the shape of the intersection is gradually emerging.
An Phu Interchange started construction at the end of 2022, with the most modern design in Ho Chi Minh City, and has received the attention and support of many people. After more than 19 months of construction, some items of the project have become visible, with some locations nearing completion. |
The Mai Chi Tho - Dong Van Cong intersection underpass is currently 70% complete, has completed some open tunnel sections and is continuing to construct the remaining open tunnel sections. |
According to current progress, the HC1-1 underpass (on Mai Chi Tho Street near Dong Van Cong) will be completed in December 2024, and the HC1-2 underpass will be completed in July 2025 (Mai Chi Tho Street connecting to the expressway access road). |
These days, workers, engineers and machines are working busily at the An Phu intersection construction site. |
Currently, the investor is renovating Mai Chi Tho Street connecting to D1 Street to serve traffic organization before constructing closed tunnel segments. |
Once completed and put into use, An Phu intersection will help solve the problem of constant traffic jams at this traffic "black spot". |
The piers of the N2 overpass branch (construction package No. 11), started on January 16, have completed the construction of 6 bored piles and installed the piers. The expected progress in May 2025 will complete the bored piles, bridge abutments, load-reducing floors and span structure. |
The project is viewed from the center of An Phu intersection towards Dong Van Cong street. |
In addition to the overpass branch construction package, other packages are also being done in parallel, some packages are waiting for site clearance. |
An Phu traffic intersection is considered especially important at the eastern gateway of Ho Chi Minh City - the starting point of the Ho Chi Minh City - Long Thanh - Dau Giay expressway connecting with main roads, so traffic jams often occur during rush hour. |
With a modern design in the style of a 3-level intersection, people hope that this project will soon be completed and solve the traffic jam that has been happening for a long time. |