Traffic congestion reduction project worth 1,200 billion VND in disarray after nearly 6 years of construction

Báo Tiền PhongBáo Tiền Phong10/03/2024


TPO - Problems in site clearance have caused the 1.5 km long road, with a total investment of up to 1,200 billion VND, to not reach the finish line after nearly 6 years of construction, affecting people's traffic.

Traffic congestion reduction project worth 1,200 billion VND in disarray after nearly 6 years of construction photo 1
The project to build a 40m road connecting Nguyen Van Cu Street to the end of the resettlement area of ​​Ngoc Thuy Ward. This is the road from the Nguyen Van Cu - Hong Tien intersection to Ngoc Thuy Street (opposite Bac Bien Park) which started in 2018.
Traffic congestion reduction project worth 1,200 billion VND in disarray after nearly 6 years of construction photo 2Traffic congestion reduction project worth 1,200 billion VND in disarray after nearly 6 years of construction photo 3
The project, once completed, will create a smooth route from Dong Tru Bridge through Thuong Thanh, Ngoc Thuy, Ngoc Lam, Bo De, Long Bien, Thach Ban wards and connect to the Hanoi - Hai Phong Expressway. In the photo is the completed Nguyen Van Cu - Hong Tien overpass.
Traffic congestion reduction project worth 1,200 billion VND in disarray after nearly 6 years of construction photo 4Traffic congestion reduction project worth 1,200 billion VND in disarray after nearly 6 years of construction photo 5Traffic congestion reduction project worth 1,200 billion VND in disarray after nearly 6 years of construction photo 6Traffic congestion reduction project worth 1,200 billion VND in disarray after nearly 6 years of construction photo 7
The entire route is 1.5 km long and 40 m wide with a total investment of 1,200 billion VND, of which more than half is for site clearance and resettlement support.
Traffic congestion reduction project worth 1,200 billion VND in disarray after nearly 6 years of construction photo 8
Many project locations have not been put into use as parking lots for people's cars.
Traffic congestion reduction project worth 1,200 billion VND in disarray after nearly 6 years of construction photo 9Traffic congestion reduction project worth 1,200 billion VND in disarray after nearly 6 years of construction photo 10Traffic congestion reduction project worth 1,200 billion VND in disarray after nearly 6 years of construction photo 11Traffic congestion reduction project worth 1,200 billion VND in disarray after nearly 6 years of construction photo 12
Up to now, the project has not been completed, the reason for the delay is problems in site clearance.
Traffic congestion reduction project worth 1,200 billion VND in disarray after nearly 6 years of construction photo 13
The highlight of the route is the steel overpass at the Hong Tien - Nguyen Van Cu intersection, with a length and approach road of about 400 m, designed with 2 lanes for motor vehicles and 2 lanes for mixed vehicles. Currently, asphalt, markings and road painting have been completed.
Traffic congestion reduction project worth 1,200 billion VND in disarray after nearly 6 years of construction photo 14
The end point of the project intersects with the dike corridor road at lane 264 Ngoc Thuy, the road with a cross-section of 40m wide has been basically completed.

Hoang Manh Thang



Source

Comment (0)

No data
No data

Same tag

Same category

Wandering in the clouds of Dalat
Villages on the Truong Son mountain range
Fall in love with the green color of young rice season in Pu Luong
Green Maze of Sac Forest

Same author

Heritage

Figure

Business

No videos available

News

Political System

Local

Product