Industrial park worth over 1,600 billion VND built for nearly 10 years is not yet completed

Việt NamViệt Nam09/09/2024


Many unfinished packages

The Technical Infrastructure Project inside and outside the fence of Nhan Co Industrial Park (Nhan Co Industrial Park) has a total investment of more than 1,658 billion VND; including 14 investment items.

khc-nhan-co-1-.jpg
Nhan Co Industrial Park project has disbursed more than 873 billion VND

The total medium-term capital for the 2016-2020 period allocated for the project is VND993 billion. Of which, the central budget is VND875 billion; the local budget is VND118 billion. To date, the project has disbursed more than VND873 billion.

Construction began in late December 2015 and the project has now implemented 8/8 construction packages, with a contract value of over 719.4 billion VND. Of these, 4/8 construction packages have been completed; the remaining 4 packages have completed 70-90% of the volume.

Specifically, the Provincial Project Management Board (PPMB) has completed 4 bid packages; of which, 1 bid package has been accepted and put into use; 3 bid packages have been completed, but have not been accepted due to volume issues with the bid package that has slipped.

There are 4 remaining packages that have not been completed. These unfinished packages are currently suspended for inspection and assessment of the cause of the collapse.

industrial-resources(1).jpg
The unfinished packages of Nhan Co Industrial Park Project are currently temporarily suspended.

The implementation of the completion of the unfinished project due to the temporary suspension of construction since 2019 is facing some difficulties. Up to this point, the project has expired, but has not been extended.

The investment capital for the project in 2024 has not been allocated. The cause of the construction incident has not been officially announced, so there is no basis for implementation...

Many problems need to be solved

Nhan Co Industrial Park project currently has many problems that need to be resolved soon to carry out the next steps.

Currently, the inspection unit has reported the cause of the collapse incident. However, to date, the inspection results of the cause of the construction incident have not been officially announced and there is no solution to fix it according to regulations.

The responsibilities of relevant individuals and organizations have not been determined. Therefore, the Project Management Board has no basis to develop a plan to overcome the subsidence problem.

industrial-resources-2(1).jpg
The results of the inspection of the cause of the incident at Nhan Co Industrial Park have not yet been officially announced to have a basis for developing a remedial plan.

Project adjustment is also facing difficulties. The Project Management Board has proactively reviewed the scale of construction items. The unit has worked specifically with the Department of Technical Infrastructure (Ministry of Construction) to agree to submit to the competent authority to divide the investment or cut some unnecessary items; then adjust the total investment to match the identified capital source.

However, the Department of Technical Infrastructure requires that in case of investment divergence or adjustment of total project investment, it is necessary to check and clarify the items invested with budget capital and the items calling for investment in the form of socialization.

At the same time, the investor clarifies the investment phases of the project's construction items. The adjusted contents must be considered by the investment decision maker to have a basis for implementation.

industrial-resources-1(1).jpg
The construction of rental prices for infrastructure assets of Nhan Co Industrial Park is facing difficulties due to the project being suspended due to subsidence incidents, and investment costs have not been settled.

Along with that, the construction of rental prices for infrastructure assets of Nhan Co Industrial Park is also facing difficulties, although it has been continuously implemented by the locality since the conclusion of the Ministry of Finance Inspectorate. However, up to now, there has been no final result.

A representative of Tran Hong Quan Metallurgy Company Limited - the investor of Dak Nong Aluminum Electrolysis Plant Project said that the project can only complete construction, equipment installation and put into operation when the technical infrastructure of Nhan Co Industrial Park is handed over in time.

Therefore, investors hope that the above difficulties will be quickly resolved so that the unit can speed up the implementation progress, promptly put the project into operation, and contribute to the overall development of the locality.



Source: https://baodaknong.vn/khu-cong-nghiep-hon-1-600-ty-dong-xay-dung-gan-10-nam-chua-xong-228719.html

Comment (0)

No data
No data

Same tag

Same category

Spectacular start of Vietnamese film market in 2025
Phan Dinh Tung releases new song before concert 'Anh trai vu ngan cong gai'
Hue National Tourism Year - 2025 with the theme "Hue - Ancient Capital - New Opportunities"
Army determined to practice parade 'most evenly, best, most beautiful'

Same author

Heritage

Figure

Business

No videos available

News

Political System

Local

Product