Dai Ngai 2 Bridge closed 7 months ahead of schedule

Báo Giao thôngBáo Giao thông05/01/2025

Dai Ngai 2 Bridge across Hau River, connecting Cu Lao Dung district with Long Phu district (Soc Trang province) officially closed after more than 1 year of construction.


On the morning of January 5, Project Management Board 85 (Ministry of Transport) held a closing ceremony for the Dai Ngai 2 Bridge Construction Project - Package No. 11-XL (crossing the Hau River, connecting Cu Lao Dung District with Long Phu District, Soc Trang Province).

Hợp long cầu Đại Ngãi 2 vượt tiến độ 7 tháng- Ảnh 1.

Delegates conduct the closing ceremony.

Mr. Le Dinh Thong, Director of Project Management Board 85, said that the project was approved by the Ministry of Transport on December 23, 2022.

This is a group A project, a special-grade road traffic project with a total investment of 7,962.148 billion VND, the investment capital is from the State budget.

The Dai Ngai 2 Bridge Project has a total route length of more than 15km, the starting point of the project intersects with National Highway 54, in Hung Hoa Commune (Tieu Can District, Tra Vinh Province), the end point intersects with Nam Song Hau National Highway, in Long Duc Commune (Long Phu District, Soc Trang Province).

Hợp long cầu Đại Ngãi 2 vượt tiến độ 7 tháng- Ảnh 2.

Dai Ngai 2 Bridge was completed 7 months ahead of schedule.

The bridge is 862m long, with a total of 13 spans, with 91 bridge girders (each girder weighs more than 80 tons, nearly 40m long). The main span, 330m long, is constructed as a cantilever structure.

Up to now, all 46/46 cantilever segments have been completed, 49/91 girder slabs have been installed, 8/13 super-T girder spans have been constructed, and the project has basically been opened to traffic on April 30, 2025.

Dai Ngai 2 Bridge, when completed, will connect Cu Lao Dung island district with the mainland, breaking the isolation of this land in the middle of Hau River.

Hợp long cầu Đại Ngãi 2 vượt tiến độ 7 tháng- Ảnh 3.

Construction progress of the entire project is about 60%.

Speaking at the closing ceremony, Mr. Lam Van Man, Secretary of Soc Trang Provincial Party Committee, highly appreciated the efforts of Project Management Board 85, the contractor and construction units who made great efforts to close Dai Ngai 2 Bridge 7 months ahead of schedule compared to the original plan.

At the same time, he requested that units continue to focus on human resources and equipment to speed up progress to open the road to traffic on April 30, 2025 as committed.



Source: https://www.baogiaothong.vn/hop-long-cau-dai-ngai-2-vuot-tien-do-7-thang-192250105111417822.htm

Comment (0)

No data
No data
More than 1,000 women wearing Ao Dai parade and form a map of Vietnam at Hoan Kiem Lake.
Watch fighter jets and helicopters practice flying in the sky of Ho Chi Minh City
Female commandos practice parade for 50th anniversary of reunification
Overview of the Opening Ceremony of National Tourism Year 2025: Hue - Ancient Capital, New Opportunities

Heritage

Figure

Business

No videos available

News

Political System

Local

Product