On March 5, the Office of the Hanoi People's Committee issued a notice of the conclusion and direction of Chairman of the People's Committee Tran Sy Thanh at a meeting to listen to reports on the implementation plan of 3 investment projects: construction of Tu Lien bridge and the approach roads at both ends of the bridge (from the intersection with Nghi Tam street to the intersection with Truong Sa street); construction of Tran Hung Dao bridge; construction of Ngoc Hoi bridge and the approach roads at both ends of the bridge and some other contents.
Construction of Tu Lien bridge started on May 19, followed by Tran Hung Dao bridge
Previously, on February 27, 2025, at the headquarters of the City People's Committee, Chairman of the City People's Committee Tran Sy Thanh chaired a meeting to listen to reports on the implementation plan of 3 investment projects: Construction of Tu Lien Bridge and access roads at both ends of the bridge (from the intersection with Nghi Tam Street to the intersection with Truong Sa Street); construction of Tran Hung Dao Bridge; construction of Ngoc Hoi Bridge and access roads at both ends of the bridge.
After listening to the report of the Department of Transport, the Management Board of Investment and Construction Projects of the City's Traffic Works, the opinions of the City's departments, branches and units attending the meeting, the opinion of Vice Chairman of the City People's Committee Duong Duc Tuan, Chairman of the City People's Committee Tran Sy Thanh concluded and directed as follows:
Implementing the direction of the General Secretary, the country is entering a new era, the "era of rising up"; the city has set a target of GRDP growth of over 8% in 2025. Therefore, to achieve this goal, all departments, branches of the city, localities, and civil servants need to change their thinking and working methods, improve the efficiency of handling and solving work, and meet the requirements of tasks in the new situation.
Regarding the time to organize the groundbreaking of investment projects: for investment projects: construction of Tu Lien bridge and the approach roads at both ends of the bridge (from the intersection with Nghi Tam street to the intersection with Truong Sa street); construction of Tran Hung Dao bridge: City leaders are determined to start the construction of Tu Lien bridge and the approach roads at both ends of the bridge on May 19, 2025 and then continue to start the construction of Tran Hung Dao bridge. Assign the Department of Transport (the Department of New Construction) to preside over and coordinate with relevant units to complete the detailed plan to ensure progress.
Regarding the route plan and location of investment projects: The City requests the Department of Planning and Architecture, the Hanoi Institute of Construction Planning, and the City Traffic Construction Investment Project Management Board to urgently coordinate with the People's Committees of relevant districts to implement the direction of the City People's Committee in Document No. 2097/VP-DT dated February 25, 2025 and Document No. 4376/UBND-DT dated December 26, 2024.
Regarding the selection of contractors to implement consulting packages for the Investment Project: construction of Tu Lien Bridge and the approach roads at both ends of the bridge (from the intersection with Nghi Tam Street to the intersection with Truong Sa Street); construction of Tran Hung Dao Bridge: assign the Department of Transport (the new Department of Construction) to preside over, together with the Department of Planning and Investment (the new Department of Finance), the City Traffic Construction Investment Project Management Board to study and apply the provisions of the newly issued law to carry out the appointment of consulting service packages, shortening the implementation time. If necessary, report to the City People's Committee for consideration and direction to report to the competent authority when implementing.
Submit to the City People's Council for decision on investment policy for the Ngoc Hoi Bridge Construction Project at the meeting in March 2025
For the Ngoc Hoi Bridge Construction Investment Project and the approach roads at both ends of the bridge: assign the Department of Planning and Investment (new Department of Finance), the Department of Transport (new Department of Construction), the City Traffic Construction Investment Project Management Board to urgently coordinate with units under the Ministry of Finance according to the direction of the City People's Committee in Document No. 1935/VP-DT dated February 21, 2025 and units of the Hung Yen Provincial People's Committee to complete the necessary documents (if necessary). On that basis, assign the Department of Planning and Investment (new Department of Finance) to advise and closely follow the content to determine the central public investment to support the target for this project, if necessary, propose and report to the City People's Committee to have a written report to the Ministry of Finance (new) and the Prime Minister.
After the Prime Minister approved the assignment of the Hanoi People's Committee as the competent authority to implement the investment project and determine the central public investment to support the project's goals, the Department of Planning and Investment (new Department of Finance) was assigned to preside over and advise the City People's Committee on procedures according to the working regulations of the City Party Committee and submit to the City People's Council for decision on the investment policy at the March 2025 meeting of the City People's Council.
Regarding site clearance and resettlement of investment projects: assign the People's Committee of Dong Anh district to urgently arrange cleared land funds in favorable locations to invest in the Resettlement Area project to serve the site clearance of 2 investment projects: Construction of Tu Lien bridge and residential roads at both ends of the bridge (from the intersection with Nghi Tam road to the intersection with Truong Sa road); construction of Tran Hung Dao bridge, construction of Ngoc Hoi bridge and other important investment projects of the city.
Assign the Department of Construction to coordinate with the districts: Hai Ba Trung, Hoan Kiem, Tay Ho, Long Bien, Hoang Mai to arrange resettlement housing funds (apartments) for cases that do not meet the conditions for resettlement by land.
People's Committees of districts (investors of site clearance component projects): when implementing land acquisition and site clearance for households within the scope of the project; districts and towns shall consider and resolve compensation and support policies and mechanisms to the maximum extent according to the provisions of law; Develop specific and detailed implementation plans and prepare necessary work to implement site clearance as quickly as possible.
City People's Committee leaders hold weekly meeting to review project progress
Assign the Department of Natural Resources and Environment (the new Department of Agriculture and Environment) to preside over, research, and advise the City People's Committee to establish a working group to advise and propose to the City People's Committee to resolve policies and regimes in site clearance to promptly remove difficulties and speed up the progress of important and key investment projects of the City.
Regarding the settlement of dossiers related to investment projects (construction of Tu Lien bridge and residential roads at both ends of the bridge (from the intersection with Nghi Tam street to the intersection with Truong Sa street); construction of Tran Hung Dao bridge; construction of Ngoc Hoi bridge and access roads at both ends of the bridge): request the city's departments, branches, and localities to thoroughly grasp, direct the implementation, handle, and resolve immediately, without delay (prioritizing "green lanes)".
In addition, assign Vice Chairman of the City People's Committee Duong Duc Tuan to direct and hold weekly progress review meetings on Thursdays on the following projects: 3 investment projects to build bridges (construction of Tu Lien bridge and access roads at both ends of the bridge (from the intersection with Nghi Tam street to the intersection with Truong Sa street); construction of Tran Hung Dao bridge; construction of Ngoc Hoi bridge and access roads at both ends of the bridge) and other projects that need to be implemented urgently and resolutely (Investment project to build Ring Road 4 - Capital Region; renovation of the space in the area east of Hoan Kiem Lake; traffic projects in the West Lake area; embellishment of the area on both sides of To Lich River).
The Chairman of the City People's Committee will chair meetings for the above projects every 2 weeks.
Source: https://kinhtedothi.vn/ha-noi-quyet-tam-khoi-cong-xay-dung-cau-tu-lien-trong-dip-19-5.html