The project includes 459m of 22kV line, 1 Recloser, 1,250kVA transformer (self-invested by the customer), with a total investment of more than 1.2 billion VND. Hangil Vina Co., Ltd. is the first large-scale electricity customer in the province to be energized after Tet At Ty 2025, with the main business being the production of lifting, lowering and loading equipment.
Nui Thanh Power Company has mobilized maximum manpower and equipment to focus on construction for 5 days, ensuring timely power supply. The project receives power from the output line after the 110kV Tam Anh transformer station.
Mr. Park Ho Heung - Construction Director of Hangil Vina Co., Ltd. expressed: “We are very satisfied and appreciate the efforts of Nui Thanh Power Company. In a short time, the unit completed the construction, acceptance and timely energization as initially committed to meet the electricity needs of our company. You are really very professional”.
Source: https://baoquangnam.vn/dien-luc-nui-thanh-hoan-thanh-cong-trinh-cap-dien-cho-khach-hang-lon-sau-tet-at-ty-3149269.html
Comment (0)