Installing an MBA to supply power to the main area where the opening ceremony of Hue National Tourism Year 2025 will take place

At this time, PC Hue focused on implementing the construction, laying nearly 700 meters of 3xM150+1xM95/0.4kV cable, installing 01 650 KVA transformer, 1 power distribution cabinet along with some synchronous accessories to supply power to the opening night area.

In addition, to ensure priority in power supply, PC Hue has strengthened the management and operation, cleared the corridors of power supply lines and has plans to prioritize power sources for transformer stations supplying power to areas where events take place in neighboring areas.

At the same time, arrange a backup generator with a capacity of 100kVA along with a standby force, increase inspection and maintenance of the generator, ensure the equipment is always ready for operation. In case of an incident related to the power grid, PC Hue will quickly handle it according to the dispatching process, ensuring timely restoration of power to the area where the opening night of the National Tourism Year - Hue 2025 will take place and the surrounding key areas.

Construction of power cable laying at the stage area on opening night

Mr. Nguyen Dai Phuc, Director of PC Hue emphasized that National Tourism Year - Hue 2025 is a meaningful event with many unique cultural and tourism activities on an inter-provincial, national and international scale.

Through these activities and programs, Hue city has the opportunity to promote its potential advantages, create a breakthrough in tourism development, attract tourists, and contribute to promoting local socio-economic growth. Ensuring stable power supply throughout the activities and programs of the National Tourism Year - Hue 2025 is the core task of all officers and employees of PC Hue.

Minh Huyen