'Only work, no back-talk' in construction of 500 kV line 3

Báo Thanh niênBáo Thanh niên29/01/2024


Also attending the conference were representatives of relevant departments, ministries, branches, the Government Office and leaders of Thanh Hoa province.

'Chỉ bàn làm, không bàn lùi' trong xây dựng đường điện 500 kV mạch 3- Ảnh 1.

Prime Minister Pham Minh Chinh chaired an online conference with relevant localities on promoting the construction progress of the 500 kV circuit 3 transmission line.

The 500kV line 3 project from Quang Trach District (Quang Binh) to Pho Noi (Hung Yen) has a total length of about 519 km, passing through 9 provinces, including: Quang Binh, Ha Tinh, Nghe An, Thanh Hoa, Ninh Binh, Nam Dinh, Thai Binh, Hai Duong, and Hung Yen. The project is invested by the National Power Transmission Corporation (EVNNPT, under Vietnam Electricity Group - EVN), with a total investment of more than 22,356 billion VND.

Reporting to the Prime Minister, Mr. Dang Hoang An, Chairman of the Board of Directors of EVN, said that the site clearance work for the project still has many problems, such as the Nam Dinh - Thanh Hoa section has only handed over 175/180 foundation positions, and 35/75 anchor spaces; the Quang Trach (Quang Binh) - Quynh Luu (Nghe An) and Quynh Luu (Nghe An) - Thanh Hoa sections have just basically completed the approval of the measurement map, and are carrying out the work of mobilizing for advance payment of compensation, mobilizing households to hand over the site to the construction contractor.

After listening to reports from localities and relevant units on the project's progress as well as the difficulties and obstacles being encountered, Prime Minister Pham Minh Chinh emphasized the viewpoint in project implementation: "only discuss action, no retreat".

The Prime Minister requested the investor and construction units to work with the spirit of "overcoming the sun and rain"; "eating and sleeping quickly"; "working in 3 shifts, 4 shifts"; "working through holidays and Tet", because this is a national key project, urgent, and plays an important role in national energy security, especially for the Northern region.

"With the spirit of not allowing power shortages for production, business and consumption in 2024 and the following years, the Government and the Government Standing Committee pay special attention to the implementation of the 500 kV circuit 3 power line projects. This is a national key project, therefore requiring the synchronous participation of relevant ministries, branches and localities, especially localities where the power line passes through. This task requires the participation of the entire political system from Party committees, authorities, social organizations to the people with high determination, great efforts, drastic actions, and focus," Prime Minister Pham Minh Chinh emphasized.

The Head of Government especially noted that this is the interest of the nation, of the people, of all people, not the business of any individual, so together with the main and core units, the entire political system must participate, mobilize total strength to implement, make up for the previous slow progress and time, determined to complete and put the project into operation before June 30.

The Prime Minister also emphasized the need for ministries, branches and localities to coordinate closely with each other in speeding up construction progress, ensuring technical and quality works; ensuring no negativity, corruption, or group interests; ensuring labor safety, preventing unfortunate incidents as well as ensuring environmental sanitation, not affecting people's lives.



Source link

Comment (0)

No data
No data

Same tag

Same category

Ta Ma - a magical flower stream in the mountains and forests before the festival opening day
Welcoming the sunshine in Duong Lam ancient village
Vietnamese artists and inspiration for products promoting tourism culture
The journey of marine products

Same author

Heritage

Figure

Business

No videos available

News

Ministry - Branch

Local

Product