Pressure to disburse, Quang Nam government implements many policies

Việt NamViệt Nam02/10/2024


Accelerating investment progress and disbursement of projects is one of the driving forces for economic development.
Accelerating investment progress and disbursement of projects is one of the driving forces for economic development.

Disbursement rate is low compared to national average

Quang Nam has thousands of projects and constructions throughout the area. Not only large capital projects are lacking in human resources, but even the provincial block with specialized management boards... are also sluggish in disbursing funds.

According to statistics from the Quang Nam State Treasury, as of September 27, 2024, public investment capital in 2024 (excluding centrally managed projects) disbursed only nearly 40.8% (VND 3,624 billion/VND 8,884 billion). This rate is lower than the same period (about 43.8% in 2023), lower than the average disbursement rate nationwide (42.63%).

The 2024 public investment capital plan only reached 38.8% (2,741 billion/7,057 billion VND). The 2023 capital plan extended the disbursement time a bit better, but still could not reach 50% when it only reached 48.3% (883 billion/1,827 billion VND). Another statistic announced that only 10/27 provincial investors and 6/18 localities achieved a disbursement rate of more than 50%.

k4.jpg
Chairman of the Provincial People's Committee Le Van Dung chaired the disbursement meetings.

According to Mr. Nguyen Hung - Deputy Director of the Department of Planning and Investment, the main reason for weak disbursement is still the lack of drastic and close management and operation. Land clearance is prolonged.

Insufficient human resources for site clearance. Lack of common construction materials, high cost compared to estimated unit price. Most projects are under lump sum or fixed price contracts, leading to some contractors implementing construction at a slow pace, waiting for updates and adjustments to construction price indexes to match market prices.

Projects using the transitional central budget must complete the planning year (2024). According to the Prime Minister's regulations, priority must be given to allocating sufficient capital for the project from the beginning of the year. When there are problems or low disbursement rates, it is still difficult to adjust the capital plan down, to switch to other projects with good volume and disbursement rates.

Chairman of the Provincial People's Committee Le Van Dung requested that by October 10, 2024 at the latest, if the capital is not spent, investors must report and propose the Provincial People's Committee to transfer capital. After October 10, 2024, if investors and localities do not report, they will be held responsible if they do not complete the project by the end of the year. The head and the person assigned to be in charge will be assessed as not completing the task.

In addition, the complex weather in mountainous areas, prolonged rain, and high risk of landslides have caused construction to be interrupted. Medical projects have encountered difficulties related to equipment valuation. Projects using ODA capital have been delayed due to the donor's review and approval of investment procedures, contractor selection plans, and capital withdrawal documents, which often take a long time.

The remaining 3 National Target Programs lack synchronous coordination, unity and high determination in direction and management from the Party Committee to the government. Many projects are stuck with forest land, planning still exists, overlapping laws and even the career capital of more than 100 million VND still has to be bid... leading to impacts on disbursement progress.

K 1
Hoi An sea embankment is speeding up progress, expected to be completed by the end of September 2024.

The reasons cited for the low disbursement rate are nothing new. Chairman of the Provincial People's Committee Le Van Dung said that the current low disbursement rate is unacceptable. We cannot blame the mechanism, policy, this or that cause.

Why is it that with the same mechanism and policy, some investors and localities disburse well, but we do not? Investors and localities must review their responsibilities and recognize their weaknesses when they cannot disburse all capital. Is it because of the lack of responsibility and determination in management and operation of investors or local authorities?

Find the best way to disburse

Investors and localities have all committed to disbursing the maximum amount of public investment capital in 2024. However, according to analysis by management agencies (Planning and Investment, Finance, State Treasury), disbursing all investment capital in 2024 is just a political determination; it cannot be done when there are only 4 months left until the end of the fiscal year.

k2.jpg
Many projects that have stopped construction will not be able to complete on schedule and disburse funds.

Mr. Nguyen Hung said that the disbursement is only 3 months away. The remaining capital to be disbursed is about 5,500 billion VND. The source extended from 2023 to 2024 is very large. This capital is only allowed to be disbursed in 2024, so investors and localities will have to prioritize the disbursement of all these extended capital sources, which is already extremely difficult.

Considering the responsibility of investors and localities when disbursement is low is something that will be done. But that is not as important as how to improve the capacity of investors to be able to spend all public investment capital in 2024. Investors and localities are committed to disbursing 100% of capital in 2023. They will review, request to transfer sources or return capital to the provincial budget.

Mr. Le Van Sinh - Chairman of Nui Thanh District People's Committee admitted that the local capacity is weak, so although they have reviewed which projects are not feasible to implement, they will transfer them, but they cannot achieve a good disbursement rate, only stopping at making advances or paying for a few large-scale projects. They will try to disburse as much as possible, especially the consulting part, and the undisbursed capital will be transferred or returned to the budget.

Actual progress shows that it is impossible to disburse 100% of the 2024 capital plan. Cutting and transferring capital to increase the disbursement rate are only temporary and situational solutions. However, in the current context, this "mechanism" is the best method.

Mr. Nguyen Hung said that we must immediately transfer within the industry, speed up the progress of central capital, and not let it drag on. Compensation and site clearance projects that have been dragging on for many years and cannot be implemented must be cut, stopped, and settled, and not allowed to drag on beyond the prescribed time...

k3.jpg
The project of Road 129 towards Nui Thanh is being accelerated.

“Investors and localities should propose early capital repayment and transfer. If they want to transfer and speed up progress, it must be completed before November 15, 2024,” said Mr. Hung.

The pressure to disburse the remaining time is too great. According to Vice Chairman of the Provincial People's Committee Tran Anh Tuan, no matter what the solution is, capital loss must be limited. 100% of the extended capital plan must be disbursed. Priority must be given to disbursing central capital.

Local leaders and investors cannot stand aside. Determine the remaining tasks in each project, investment phases, and from there consider which ones should be transferred and which ones should be resolutely disbursed. Any project or work that is subject to force majeure must be determined to be transferred before November 15, 2024.

Chairman of the Provincial People's Committee Le Van Dung requested investors and localities to have the highest determination to achieve the best disbursement rate. Investors should proactively check and review the disbursement capacity of each specific project with a low disbursement rate to propose to competent authorities to adjust the capital plan to projects that ensure volume and can be disbursed immediately upon receiving additional capital sources within each unit or propose to competent authorities to adjust the annual capital plan to transfer to units and localities in need of additional capital in the upcoming Provincial People's Council meeting scheduled for the end of October 2024. Prioritize the allocation of sufficient funds to carry out compensation and site clearance for areas that meet the conditions. Avoid the situation of projects waiting for site clearance, "soaking" capital, reducing the efficiency of project investment. Regularly report on project progress (every two weeks).



Source: https://baoquangnam.vn/ap-luc-giai-ngan-chinh-quyen-quang-nam-trien-khai-nhieu-ke-sach-3142085.html

Comment (0)

No data
No data

Same tag

Same category

Overseas Vietnamese player Le Khac Viktor attracts attention in Vietnam U22 team
The creations in the TV series 'Remake' left an impression on Vietnamese audiences
Ta Ma - a magical flower stream in the mountains and forests before the festival opening day
Welcoming the sunshine in Duong Lam ancient village

Same author

Heritage

Figure

Business

No videos available

News

Ministry - Branch

Local

Product