80% of disaster recovery capital in Dak Nong has not been disbursed

Việt NamViệt Nam23/10/2024


On the afternoon of October 23, TUV, Vice Chairman of Dak Nong Provincial People's Committee Le Trong Yen chaired a meeting to listen to a report on the implementation of overcoming the consequences of natural disasters and landslides caused in 2023 in Dak Nong.

img_8436-1-.jpg
The disbursed budget to overcome the consequences of natural disasters and landslides in 2023 in Dak Nong is only over 45.4 billion VND, reaching nearly 20% of the plan.

As of October 21, 2024, Dak Nong has 31 projects under construction and completing documents and procedures for selecting contractors. The total disbursed budget of the projects and works is over 45.4 billion VND, reaching nearly 20% of the allocated capital plan.

The disbursement results were low due to many reasons. First of all, the weather in recent months has been heavy and prolonged rain, affecting the implementation of work.

The process of mobilizing households to donate land in some projects to overcome the consequences of natural disasters encountered difficulties. The periodic reporting of implementation results by some units and investors did not ensure the prescribed time.

img_8446(1).jpg
Chairman of Tuy Duc District People's Committee Dinh Ngoc Nhan presented difficulties in site clearance in the locality.

Regarding difficulties in capital disbursement, Chairman of Tuy Duc District People's Committee Dinh Ngoc Nhan said that during the implementation process, the district encountered difficulties in site clearance.

“Provincial Road 1 project in Quang Truc commune accounts for about 90 billion VND in allocated funds. Currently, the project is stuck with site clearance for 25 households. Of these, 2 households have permanent houses. We have been and are working on a solution, striving to disburse all capital in 2024,” said Mr. Nhan.

img_8451(1).jpg
Representative of People's Committee of Krong No district (Dak Nong) mentioned some difficulties in implementing works and projects.

Regarding the progress of capital disbursement, Mr. Le Trung Kien, Chief of Office of the Dak Nong Provincial Steering Committee for Natural Disaster Prevention and Search and Rescue, said that there are many projects and little time left.

Therefore, investors are focusing on accelerating the volume and disbursement of capital. Localities are completing investment procedures and documents related to projects.

Concluding the meeting, Vice Chairman of the Provincial People's Committee Le Trong Yen emphasized that there is very little time left in 2024, the weather is entering the dry season, and investors are speeding up construction progress.

By December 31, 2024, any locality or investor that fails to fully disburse and return capital to the Central Government must be responsible to the Provincial People's Committee.

img_8438(1).jpg
Vice Chairman of the Provincial People's Committee Le Trong Yen requested investors to speed up disbursement progress and improve project quality.

For projects with few problems, investors should speed up progress, have volume, and disburse funds immediately. Along with progress, the quality of construction and projects need to be strictly controlled.

Regarding site clearance, investors should propagate and mobilize people. How to make people understand the importance of overcoming incidents, ensuring construction safety and safety for people.

“The investor must be flexible in directing and operating. The preparation of human resources to implement the project needs to be focused on. Supervision work to enhance responsibility for implementing works and projects must be promoted, minimizing the amount of capital returned to the Central Government,” emphasized Vice Chairman of the Provincial People's Committee Le Trong Yen.



Source: https://baodaknong.vn/80-von-khac-phuc-thien-tai-o-dak-nong-chua-duoc-giai-ngan-232416.html

Comment (0)

No data
No data

Same tag

Same category

Spectacular start of Vietnamese film market in 2025
Phan Dinh Tung releases new song before concert 'Anh trai vu ngan cong gai'
Hue National Tourism Year - 2025 with the theme "Hue - Ancient Capital - New Opportunities"
Army determined to practice parade 'most evenly, best, most beautiful'

Same author

Heritage

Figure

Business

No videos available

News

Political System

Local

Product