In 2023, the leaders of Binh Thuan province have resolutely directed and prioritized state budget capital managed by the province and central budget capital invested in the area to promote investment in key projects of the province.
Up to now, many projects have been invested and ensured progress and capital disbursement plan. However, the delay in resolving difficulties and inadequacies in compensation, support, and resettlement arrangements for land acquisition to serve the construction of public investment projects has affected the progress of implementation,... The preparation of documents and procedures for implementing public investment projects is still slow, leading to insufficient conditions for investment capital allocation. Disbursement of public investment capital is still slower than planned.
Embankment of the left bank of Ca Ty River (section from Duc Thanh Bridge to Ung Van Khiem Street)
The project belongs to Group B, with a total investment of about more than 486 billion VND, from the provincial budget. The project implementation period is 4 years, phase 2021 - 2025 and transition to phase 2026-2030, and has not yet been constructed. The 2023 plan allocates 100 million VND to carry out investment preparation work, the project is allocated from the reserve capital in the public investment plan for the period 2021-2025 and excess revenue capital.
Ka Pet Reservoir
The project includes 3 items: a reservoir with a capacity of 51 million m3, a headworks and a water channel system. The total investment and capital of the project is more than 874 billion VND (the central budget is more than 519 billion VND and the local budget is more than 354 billion VND). In particular, in the central budget, 47.3 billion VND is the reserve capital that has been extended for disbursement until December 31, 2023. This is the central budget capital supporting the climate change response and green growth program. Currently, the consulting unit is completing the contents of the dossier according to the new decree to submit to the Ministry of Natural Resources and Environment for appraisal. After that, it will develop a plan for exploitation, auction, contractor selection and construction commencement. Although there are still many difficulties in the time to complete procedures, the province is determined to ensure the progress of the project as set out, expected to start construction in the second quarter of 2024 and complete after a year and a half to supply water to the people.
Storm shelter area combined with Phu Quy fishing port (phase 2)
The project is being submitted to the Department of Fisheries - Ministry of Agriculture and Rural Development for appraisal of construction drawing design - estimate, and is expected to organize bidding and hand over the construction site in December 2023. The capital plan for the period 2021-2025 is 450 billion VND; the capital in 2022 is 1,150 billion VND, disbursed by January 31, 2023 reaching 100%; the capital plan in 2023 is 50 billion VND, currently disbursed 927 million VND.
Van Thanh Bridge
Construction started on December 30, 2022, expected to be completed on December 19, 2024, currently construction has reached about 2% of the contract volume. The capital plan for the period 2021-2025 is 225 billion VND (central budget). The accumulated capital arrangement for the period 2021-2023 is 125.1 billion VND (of which: The capital plan for 2023 is 70 billion VND, not yet disbursed). Currently, the contractor has completed driving 415 Iarsen piles to create a steel sheet pile enclosure to construct pillars T4, T5, pier M2 (Phu Tai ward side) and is pumping sand to create a construction site for the above items. During the construction process, the province regularly held meetings to check the progress of the project, thereby directing relevant units to focus on speeding up the construction progress, removing obstacles to speed up the construction progress, removing obstacles to speed up the compensation and site clearance work.
Provincial Theater and Exhibition of Culture and Arts
The construction package is expected to complete the rough construction by the end of September 2023, including: reinforced concrete, wall plastering, erection of steel truss systems and roof space truss systems. After adjusting the design and completing the roofing work, the construction unit is continuing to complete the related work... The remaining packages are expected to be completed by the end of 2023. The expected completion date of the project is December 2023. The capital arrangement situation to date is 190,499 billion VND and disbursement is 126,955 billion VND.
Coastal axis road DT.719B, Phan Thiet - Ke Ga section
In 2023, the capital plan is 234,650 billion VND and the disbursement is 48,910 billion VND (construction and installation costs 12,034 billion VND, compensation and clearance 36,876 billion VND). The accumulated value of implementation to date is 804,665 billion VND (construction and installation costs 431,760 billion VND, construction and installation advances 84,458 billion VND, other costs 29,620 billion VND, compensation and clearance 258,827 billion VND).
Ca Ty River Apartment, Phan Thiet City
The total investment of the project is 799 billion VND, of which construction costs account for more than 577 billion VND; contingency costs are 72 billion VND... The project has almost no compensation and clearance costs. Legal procedures and site clearance will be completed in the period from May to August 2023. Construction will begin in the period from October 2023 to September 2024. The works will be tested in the period from October 2024 to December 2024. Operation will begin in January 2025.
Phan Thiet Airport
The military airport construction investment project is expected to be completed and put into use in early 2024. Currently, the project progress of implementing the construction of military items and runways is being accelerated. Particularly, the civil aviation item under the form of BOT contract, due to the adjustment of the scale from level 4C airport to level 4E, must re-implement the investment policy procedures. Currently, the province has directed the termination of the project contract signed with the old unit to implement the procedures for re-selecting investors according to regulations, and at the same time invited an independent auditing unit to evaluate and determine the investment value of the old unit to consider refunding the costs. The project has completed the entire 542-hectare airport site, the navigation tower and a number of related items. Currently, the project is implementing compensation and site clearance for a number of additional items.
Source
Comment (0)