Dong Nai: Progress in implementing the general planning of Long Khanh city is still slow.
Although the Dong Nai Provincial People's Committee has approved the planning tasks of each subdivision, up to now, Long Khanh City has not yet completed the implementation of the planning project according to regulations.
As of January 17, 2021, the People's Committee of Dong Nai province issued Decision No. 5100/QD-UBND approving the overall adjustment of the 1/10,000 scale master plan of Long Khanh City to 2040, with a vision to 2050.
After that, Long Khanh City People's Committee established planning tasks for 10 sub-zones according to the master plan and the Provincial People's Committee issued Decisions approving the planning tasks of the above 10 sub-zones on July 4, 2023. After the sub-zone planning tasks were approved, Dong Nai Provincial Department of Construction issued documents to deploy, guide and urge Long Khanh City People's Committee to establish 1/2000 scale sub-zone planning projects for the 10 sub-zones.
Long Khanh City is organizing bidding for consulting packages to survey and develop planning projects for 10 subdivisions according to regulations. |
However, after more than 2 years of approval for the overall adjustment of the 1/10,000 scale master plan and more than 1 year of approval for the tasks, the planning of 10 subdivisions in Long Khanh City is still stuck and the planning project cannot be established within the prescribed time.
Difficulties and obstacles are mainly in the bidding stage. For example, the organization of bidding to select a planning consultancy unit. The preparation of the zoning plan for 10 sub-zones takes more time because it is necessary to organize the selection of contractors through open bidding. Stipulated in Point m, Clause 1, Article 23 and Clauses 1,2, Article 21 of the Bidding Law 2023.
Currently, the Long Khanh City Urban Management Department is organizing bidding for survey consultancy packages and planning projects for 10 subdivisions according to regulations. All bid packages have been opened and the consulting unit is evaluating the bidding documents.
Regarding the implementation of planning in Long Khanh City, the acting Chairman of the Provincial People's Committee, Vo Tan Duc, has directed the Department of Construction to review the zoning planning documents currently being implemented in Long Khanh City and focus on this work to ensure progress and quality, determined to complete it by the end of 2024 to serve as a basis for attracting investment and implementing projects.
Accordingly, by April 2024, the Provincial People's Committee has approved the funding for the implementation of 10 subdivisions. Based on the funding, Long Khanh City has invited units to bid. Up to this point, the project is in the process of selecting contractors to implement the projects and the progress is currently on schedule.
According to the general planning of Dong Nai province until 2040, Long Khanh city is a type II urban area under the province, a central urban area in the eastern part of Dong Nai province, a counterweight development pole in the eastern part of Ho Chi Minh City; an industrial and supporting industrial center of the province and Ho Chi Minh City region; a regional trade and service center; a center for trading goods and warehousing agricultural and forestry products of the province; a regional center for agricultural eco-tourism, culture and history and a traffic hub of the region, connecting provinces in the Southeast and Central Highlands regions.