Focus on synchronously implementing solutions to disburse public investment capital

Việt NamViệt Nam26/03/2024

2024 is a year of special significance in successfully implementing the Medium-Term Public Investment Plan for the period 2021-2025. Therefore, right from the first months of the year, departments, branches and localities in the province have identified the task of implementing and disbursing public investment capital as one of the top important tasks, focusing on implementation, striving to ensure the disbursement rate reaches over 95% of the assigned plan.

Speed ​​up implementation

Nho Quan is a locality that is focusing on implementing many important works and projects, in which the East-West Road Construction Investment Project (Phase I) is identified as a key project of the province, which must be completed as soon as possible to create momentum and a breakthrough in the socio-economic development of the province in the immediate future and has a strategic and long-term vision. Therefore, Nho Quan district has mobilized the entire political system to participate in propagating and mobilizing the people of 5 communes (Cuc Phuong, Ky Phu, Phu Long, Van Phuong, Van Phong) to agree with the compensation and support plans for site clearance (GPMB).

Up to now, the district has completed the road clearance work, 100% of households in communes whose houses had to be relocated have voluntarily dismantled and relocated; ensuring the entire route is clear; 100% of agricultural land area has completed compensation payment in accordance with current legal regulations.

In addition to carrying out compensation for site clearance according to regulations, the district has also carried out the work of moving technical infrastructure, and has completed about 95% of the electrical work; 95% of the telecommunication cable work. Currently, there are 2 locations where the construction site has just been available at the intersection of National Highway 45 (Phu Long commune) and the intersection of Bai Dinh-Cuc Phuong road (Ky Phu commune), so the moving work has not been completed.

Regarding resettlement and land allocation, the district has arranged 4 resettlement areas and 2 on-site resettlement land allocation areas (Cuc Phuong, Van Phong). Up to now, the procedures for investing in infrastructure construction projects for resettlement areas have been completed and resettlement land has been allocated to 67 households in need.

Comrade Dang Xuan Nguyen, Member of the Provincial Party Committee, Secretary of the Nho Quan District Party Committee emphasized: After 2 years of implementing the site clearance work, the East-West Road Construction Investment Project (Phase I) through Nho Quan District has been basically completed, 1.5 months ahead of the plan assigned by the Provincial People's Committee. This demonstrates the great efforts of the Party Committees and authorities at all levels, the solidarity and consensus of cadres, party members and people of Nho Quan District, and especially the regular, responsible and timely coordination of the investor and contractor with the local government, with the common desire to contribute to the construction of the largest connecting road ever, opening up space, creating new space and momentum to promote rapid and sustainable socio-economic development of Ninh Binh Province in general and the localities where the project passes through in particular.

With the goal of soon and successfully completing the entire Public Investment Plan, right from the first days and months of the year, investors, project management boards, and local People's Committees have quickly implemented solutions to accelerate construction progress, project quality, and disbursement of public investment capital, typically: Ninh Binh-Hai Phong Expressway Construction Investment Project, section through Ninh Binh province; North-South Expressway Expansion Project, Eastern section, Cao Bo-Mai Son; 500kV Power Transmission Line 3 Circuit Project from Quang Trach (Quang Binh) to Pho Noi (Hung Yen); East-West Road Construction Investment Project, Ninh Binh Province (Phase I); DT.482 Road Construction Investment Project connecting National Highway 1A with National Highway 10 and connecting National Highway 10 with National Highway 12B; Project to upgrade and expand the main road to Kenh Ga stream tourist area and Van Trinh cave (Phase II); Project to build a tourist route combined with urban development from Thien Ton town to Hoa Lu ancient capital...

Synchronize solutions

In 2024, the total public investment plan of Ninh Binh province is allocated 6,539,603 billion VND, including: Central budget capital is 611,380 billion VND; local budget capital is 5,928,223 billion VND. Up to this point, the capital sources have been allocated and detailed by the province and localities for projects and works, ensuring compliance with State regulations. With the efforts of all levels and sectors in the province, the total development investment capital implemented in the first 2 months of the year reached 4,780.1 billion VND, an increase of 4.9%.

The province has proactively, synchronously and effectively implemented tasks and solutions to promote the disbursement of public investment capital, especially the acceptance, payment and settlement of completed projects. In particular, it has proactively developed implementation plans and disbursement progress for each task and project under the central budget and local budget investment plan for 2024 assigned by the Provincial People's Committee.

In the first two months of the year, the total disbursed capital reached 723.95 billion VND, reaching 11% of the assigned capital plan. Including: Central budget disbursed capital was 9,650 billion VND, reaching 1.5% of the assigned capital plan; local budget disbursed capital was 714.3 billion VND, reaching 12% of the assigned capital plan.

To ensure the disbursement rate reaches over 95% of the assigned plan as required by the Prime Minister, in the coming time, the Provincial People's Committee directs all levels, sectors, and investment units to focus on implementing drastic and effective solutions to promote disbursement of public investment capital, clearly identifying this as a key political task of great significance to create momentum to accelerate the recovery and socio-economic growth of the province associated with ensuring quality, fighting negativity, corruption and waste.

Continue to accelerate the progress of investment preparation, investment decision, design establishment, appraisal, approval, implementation after basic design, contractor selection to soon start construction of new projects expected to start construction in 2024, especially projects expected to allocate increased revenue from the Central budget. Seriously review and focus on resolving land acquisition and site clearance problems, ensuring the construction of key projects and works according to the set schedule.

Nguyen Thom


Source

Comment (0)

No data
No data

Same tag

Same category

Spreading national cultural values ​​through musical works
Lotus color of Hue
Hoa Minzy reveals messages with Xuan Hinh, tells behind-the-scenes story of 'Bac Bling' causing global fever
Phu Quoc - tropical paradise

Same author

Heritage

Figure

Business

No videos available

News

Ministry - Branch

Local

Product