Overview of the working session. |
The 500kV line 3 project from Quang Trach to Pho Noi in Hung Yen province has a total length of about 519 km, passing through 211 communes and wards of 43 districts and towns in 9 provinces. Nghe An is currently implementing 2 projects, including: Quang Trach - Quynh Luu 500kV line project with 168 pole foundation locations and Quynh Luu - Thanh Hoa 500kV line project with 34 pole foundation locations.
In Nghe An province, 156/202 pole positions have been erected and the wire pulling is entering the final stage. |
Up to now, the column foundation casting has been completed, 156/202 column positions have been erected and the wire pulling is entering the final stage.
Construction site of 500kV Line 3 project in Nghe An province. |
At the meeting, Vietnam Electricity Group proposed to the People's Committee of Nghe An province to continue directing departments, branches and localities to better coordinate with investors and construction units to resolve problems arising during the construction process.
Deputy General Director of Vietnam Electricity Group Pham Hong Phuong spoke at the meeting. |
General Director of National Power Transmission Corporation Pham Le Phu spoke at the meeting. |
With the requirement to ensure progress according to the direction of the Prime Minister, Standing Vice Chairman of the Provincial People's Committee Le Hong Vinh requested relevant departments, branches and localities to be resolute in urging and opening temporary service roads, creating a safe corridor for units to construct the 500kV Line. Particularly, localities where the project passes through need to coordinate with functional forces, organize to ensure security and order, resolve cases of intentional obstruction, and ensure the set progress.
Permanent Vice Chairman of the Provincial People's Committee Le Hong Vinh spoke at the meeting. |
For better coordination, Standing Vice Chairman of the Provincial People's Committee Le Hong Vinh also requested Vietnam Electricity Group and the National Power Transmission Corporation to proactively compile and review specific tasks. Especially at the present time, Nghe An province requests construction units to prepare plans to respond to extreme weather, ensuring safety for people, works, machinery and equipment at the construction site. More importantly, the investor and contractors must fulfill their commitment to restore the land and residential roads along the entire route after completing the project./.