Dien Chau district authorities are urgently implementing compensation and site clearance for the expansion so that investors can soon build and complete the rest stop on the highway section through Nghe An.
Efforts to soon hand over the site to investors
In late December 2024, Giao thong Newspaper reporters were present along the entire route and recorded that both component projects had been completed, allowing vehicles to move easily and conveniently.
The rest stop on the highway section through Nghe An was built in Hanh Quang commune, Dien Chau district.
Meanwhile, the official rest stop in Nghe An province is located at Km 427+035 (in Hanh Quang commune).
The North-South Expressway section through Nghe An province has a total length of nearly 88km, including 2 component projects: Nghi Son - Dien Chau and Dien Chau - Bai Vot.
"The location of the rest stop in Dien Chau district is very suitable, because it is located in the middle, dividing the distance from Thanh Hoa to Ha Tinh," said Nguyen Van Tam, a driver living in Dien Chau district.
Mr. Nguyen Manh Ho - Chairman of the People's Committee of Hanh Quang Commune, Dien Chau District said that the rest stop has been compensated, and more than 4 hectares of land has been cleared. Currently, the remaining 2.6 hectares of the expansion are being urgently cleared by the locality.
Specifically, on the west side of the road, for traffic from Hanoi to Vinh, due to the 220kV power line, the current status of the cleared land will remain. On the contrary, on the east side of the road, for traffic from Vinh to Hanoi, an additional 2.6 hectares will be expanded.
According to Mr. Ho, this land previously belonged to the people of Dien Hanh and Dien Quang communes, now merged into Hanh Quang commune.
"100% of the expanded land is from 2-rice land. In the recent meetings and area confirmation signings, most of the people agreed to hand over the land to the investor for the rest stop. The commune will continue to promote so that when the procedures are complete, compensation will be paid immediately so that the investor can start construction soon," Mr. Ho added.
Mr. Le Manh Hien - Vice Chairman of Dien Chau District People's Committee added: 2.6 hectares of expanded area of 54 households in Hanh Quang commune. This project was acquired by the district and then handed over to the Petrolimex joint venture for investment and construction.
"The district is focusing on and coordinating with the investor and relevant parties to make efforts to speed up the compensation and site clearance progress to hand over to the investor. This is a national key project, which has great significance for the socio-economic development of the whole country. During the compensation process, the district site clearance council always implements it openly and democratically; fully and best ensures the rights of the people and complies with the law. Therefore, we hope that the affected people will agree and support the project so that it can be implemented soon," Mr. Hien shared.
The area where the rest stop is built is mostly agricultural land.
Complete the procedures and construction will begin immediately.
Through the investigation of the reporter, in early July 2024, the Director of the Vietnam Expressway Administration signed a decision approving the results of the selection of investors for the Project to invest in the construction and operation of the Km 427+035 rest stop under the Nghi Son - Dien Chau component project on the North - South expressway, Eastern section.
The winning bidder is the Petrolimex consortium (including Vietnam National Petroleum Group and Thua Thien - Hue Petroleum Company).
The value in cash paid to the State budget for this project is 86 billion VND; the preliminary value of the project implementation cost is 196.397 billion VND; the value of compensation, support and resettlement is 16.743 billion VND.
This project has an overall progress of 17 months, of which the time to complete public service works is 11 months. The project exploitation period after completing the investment work is 25 years.
According to the environmental impact assessment report published by Petrolimex, the land area surveyed for detailed project planning is about 8.9 hectares.
Speaking over the phone, a Petrolimex leader in charge of this rest stop project said that the unit is urgently completing the procedures. Once completed, construction will begin immediately.
The North-South Expressway section through Nghe An province has a total length of nearly 88km, including 2 component projects.
The Nghi Son - Dien Chau section of the project has a total length of 50km, passing through Nghe An province for 43.5km. The project has a total investment of VND 7,293 billion, starting construction in July 2021 and being put into operation from September 1, 2023.
The Dien Chau - Bai Vot section of the project is 49.3km long, passing through Nghe An province for 44.4km. The project is implemented in the form of public-private partnership (PPP), with a total investment of VND 11,157 billion. The project started on May 22, 2021, has been completed to date, and is expected to officially collect tolls on January 5, 2025.
The expressway through Nghe An province has 5 intersections, including: QL48D (in Quynh Vinh commune, Hoang Mai town); QL48B (in Quynh My commune, Quynh Luu district); QL7A (in Dien Cat commune, Dien Chau district); QL7C (also known as N5 road, in Nghi Dong commune, Nghi Loc district) and finally QL46B intersection (in Hung Tay commune, Hung Nguyen district).
Currently, authorities are arranging two temporary rest stops at the two ends of Truong Vinh tunnel and Than Vu tunnel.
Source: https://www.baogiaothong.vn/tap-trung-gpmb-som-xay-dung-tram-dung-nghi-tren-cao-toc-qua-nghe-an-19224122510535486.htm