Vice Chairman of the Provincial People's Committee Hoang Viet Phuong inspected the construction progress of Tuyen Quang Specialized High School at the new location. Photo: Huy Hoang
Tuyen Quang Specialized High School project at the new location on an area of 6 hectares, with a total investment of 255 billion VND; scale of 38 classes, over 1,300 students, of which about 400 are boarding students.
Up to now, the project has completed over 80% of the work volume, ensuring that it will be handed over to the investor before August 15, 2024. Work related to site clearance, planning, basic design, construction drawing design, construction bidding and supervision consultancy has been completed. There is currently 1 equipment procurement package and 1 bidding package to hire consultants to carry out environmental licensing, m. The Department of Education and Training is carrying out procedures for preparing, appraising, approving estimates... to invite bids according to regulations.
The Vice Chairman of the Provincial People's Committee inspected the progress of the Tuyen Quang Provincial General Hospital construction project. Photo: Huy Hoang
The Tuyen Quang Provincial General Hospital construction project has a total area of over 16 hectares; the total investment is 1,796 billion VND from the central budget and local budget. The hospital has a scale of 1,000 beds, including all items according to the standards of a grade I provincial general hospital, the project is invested by the Department of Construction.
The project started on December 6, 2023. After 4 months since the start of construction, the progress of the bidding packages up to now has basically met the approved project implementation plan.
Leaders of the Department of Education and Training reported on the progress of the Tuyen Quang Specialized High School Construction Project at the new location. Photo: Huy Hoang
Up to now, 16,578/16.58ha of land has been cleared; the total number of households that have to clear land is 181, and 1 household illegally built on the stone embankment and fence of the project (built after the planning was approved), with an area of 25m2, so contractors have not been able to construct this area, thus affecting the overall progress of the project and the bidding packages.
Currently, the construction units of the Provincial General Hospital project are concentrating on machinery, speeding up the construction progress of the main items as well as the auxiliary items. However, the site leveling process is facing some difficulties due to lack of fill soil and obstacles in site clearance, affecting the progress.
Vice Chairman of the Provincial People's Committee Hoang Viet Phuong concluded the meeting. Photo: Huy Hoang
Speaking at the working session with investors, Vice Chairman of the Provincial People's Committee Hoang Viet Phuong acknowledged the efforts of investors, contractors, and Tuyen Quang city in implementing projects, especially site clearance for projects.
He emphasized that these are two projects of great social significance to the province. Regarding the Provincial General Hospital project, the province identifies it as a final-level hospital, meeting the needs of medical examination and treatment, taking care of people's health, worthy of the region.
Currently, the project still has some slow items such as the treatment block, examination department, infectious disease department, waste treatment center, funeral home...
The Vice Chairman of the Provincial People's Committee requested that contractors need to focus on human resources, equipment, and conditions to ensure the construction process; investors should strengthen coordination with departments and construction units to overcome difficulties and obstacles during the implementation process.
He assigned the City People's Committee to complete and report to the Provincial People's Committee before May 15 on the settlement of households illegally building on the stone embankment and fence construction site of the project so as not to affect the construction progress.
Regarding the Tuyen Quang High School for the Gifted project, the Vice Chairman of the Provincial People's Committee requested the investor to concentrate on completing the project on schedule; pay attention to labor safety; review the entire workload to organize effective construction, and strive to put the school into operation on the opening day of the new school year.
Vice Chairman of the Provincial People's Committee Hoang Viet Phuong assigned the Department of Planning and Investment and the Department of Finance to review capital sources and complete the report to the Provincial People's Committee before May 15.