Kinhtedothi-On the morning of February 6, Deputy Secretary of the City Party Committee, Chairman of the Hanoi People's Council Nguyen Ngoc Tuan visited, wished a Happy New Year and encouraged cadres, workers and laborers at the construction site of the Ring Road 4 - Hanoi Capital Region construction investment project through Thuong Tin district.
Director of Hanoi Traffic Construction Investment Project Management Board Ngo Ngoc Van quickly reported to Chairman of the City People's Council Nguyen Ngoc Tuan about the project's progress.
Accordingly, up to now, the project's site clearance has reached nearly 99%, grave relocation has reached over 99%; 13/13 resettlement areas have been completed and 35% of households have been resettled; 10/16 high-voltage power intersections have been relocated. It is expected to strive to complete the entire project's site clearance in the first quarter of 2025.
Road construction progress is parallel with site clearance work, after about 19 months from the start date, with 32 construction sites along the entire route; the volume of roadbed embankment has reached about 85%; crushed stone grading is about 35%; and construction of bridges, culverts and other items is carried out simultaneously.
In Me Linh, Dan Phuong, and Hoai Duc districts, about 15km of asphalt concrete has been constructed. The contractor for Package No. 11 in Thuong Tin district has taken over the entire length of the package, which is 9.3km, and has completed the roadbed, soft soil treatment, and river bridges. The total output of the parallel road project has so far reached about 50% of the contract value and the project is expected to be completed in the fourth quarter of 2025.
Currently, the city has issued bidding documents to select investors for component project 3 and opened bidding on March 7, 2025. It is expected to complete the selection of investors and start the project in the second quarter of 2025 if there are qualified investors.
Wishing a Happy New Year and encouraging contractors, supervisory consultants and all employees and workers working at the Ring Road 4 Construction Investment Project - Capital Region, Chairman of the Hanoi People's Council Nguyen Ngoc Tuan praised the serious and active working spirit of the units, including Thuong Tin district, which has done a good job of site clearance so that contractors have space to implement the project.
Chairman of the City People's Council Nguyen Ngoc Tuan emphasized that the investment project to build Ring Road 4 - Hanoi Capital Region was approved by the National Assembly in Resolution No. 56/2022/QH15 dated June 16, 2022 and the Government guided the implementation in Resolution No. 106/NQ-CP dated August 18, 2022, with the basic progress of completion in 2026 and put into operation from 2027. This is an important, national key project, of great significance to the socio-economic development of Hanoi Capital in particular and the provinces in the Capital Region, the Red River Delta and the Northern Key Economic Region. The project has a regional connectivity nature, linking with expressways, radial routes, connecting Hanoi City with neighboring provinces.
Chairman of the Hanoi People's Council Nguyen Ngoc Tuan said that in the past time, the entire political system of the city and districts have focused very strongly, creating solidarity, unity, and consensus from the city to the grassroots and receiving high consensus and support from the people. Up to now, the project has achieved positive results - in particular, workers have worked through Tet to ensure the project's progress.
Chairman of the Hanoi People's Council Nguyen Ngoc Tuan requested the project investor, construction contractor, supervision consultant and all employees and workers working at the Ring Road 4 - Capital Region Construction Investment Project in Hanoi to closely follow the plan and progress, strive to complete the construction with quality and safety; focus on implementing component projects and auxiliary works.
“During the implementation process, if there are any difficulties or problems, they need to be reported and proposed to the city in the spirit that wherever there is land, construction must be carried out promptly and the project must not be delayed,” emphasized Chairman of the City People's Council Nguyen Ngoc Tuan.
Committing to make efforts to implement according to schedule, the Hanoi Traffic Construction Investment Project Management Board, representative of the Joint Venture of Bidding Package No. 11 (CIENCO4 Group Joint Stock Company - Hoang Long Construction and Trading Joint Stock Company - Song Hong Joint Stock Company) is implementing the package in Thuong Tin district, committed to overcoming difficulties so that the project can be completed on time, ensuring quality and safety.
Source: https://kinhtedothi.vn/no-luc-de-hoan-thanh-tien-do-du-an-duong-vanh-dai-4-vung-thu-do.html
Comment (0)