After more than 1 year of implementation, the contractors constructing the Ring Road 4 - Capital Region have basically completed the foundation and roadbed and are paving the first kilometers with asphalt concrete.
According to the reporter, in the XL8 package passing through the two districts of Dong Anh and Me Linh, the contractor Truong Son Construction Corporation has completed more than 35% of the construction and installation volume. The section passing through Tan Dan commune (Dong Anh) is the highlight of the progress when the asphalt concrete layers have been laid in preparation for completion. (In the photo, the contractor mobilized 50 workers and machines to deploy the asphalt paving).
Sharing with us, a worker operating a paving machine said that this is the first section to be paved in the Ring Road 4 - Capital Region Project. The road is currently being paved with C25 hollow asphalt, and will have to be paved with two more layers.
The construction unit can pave 200m of road surface per day. (In the photo, workers are performing the road paving process).
The road when paved with C25 hollow asphalt.
With the construction package of Ring Road 4 through Hoai Duc district, the unit has completed the weak soil part and paved the base stone for about 4km. The total construction volume has reached about 30%.

The Ring Road 4 Project - Hanoi Capital Region has a total length of 112.8 km, passing through 3 cities and provinces, including Hanoi (57.95 km), Hung Yen (19.31 km), Bac Ninh (36.26 km). The project has a total investment of over 85,813 billion VND, divided into 7 component projects. The project started on June 25, 2023 and is scheduled to complete the parallel road according to the project approval in 2026, completing the expressway in 2027.
The Hanoi Traffic Construction Investment Project Management Board (investor) of the Ring Road 4 - Capital Region project said that the parallel road (urban road) of Ring Road 4, the section through Hanoi, is more than 57km long, passing through the districts: Ha Dong, Dong Anh, Me Linh, Hoai Duc, Thuong Tin... The project's basic completion time is expected to be in 2025 by the investor and contractors.
Panorama of the first meter of asphalt on Ring Road 4 - Capital Region:
Source: https://www.baogiaothong.vn/nhung-met-tham-dau-tien-tren-tuyen-vanh-dai-4-vung-thu-do-192240823074518852.htm