A bid package of the 4,800 billion VND project through Tan Son Nhat airport is at risk of "breaking" progress.

Báo Giao thôngBáo Giao thông30/09/2024


On September 30, a representative of the Ho Chi Minh City Traffic Construction Investment Project Management Board (Traffic Board) said that they had proposed many problems to the Steering Committee for Key Projects of Ho Chi Minh City. Among them, the difficulty of Package No. 13, the end of the Tran Quoc Hoan - Cong Hoa connecting road, is at risk of greatly affecting the expected traffic opening progress.

Một gói thầu thuộc dự án 4.800 tỷ qua sân bay Tân Sơn Nhất có nguy cơ

The road connecting Tran Quoc Hoan - Cong Hoa (red section) passes through the land belonging to Tan Son Nhat airport.

The Tran Quoc Hoan - Cong Hoa connecting road project is about 4km long, with a total investment of more than 4,800 billion VND, starting construction in December 2022.

With the goal of clearing the entire area that has been congested for many years, the route is designed with 6 lanes, passing through the land belonging to Tan Son Nhat airport and connecting directly to Terminal T3, Tan Son Nhat International Airport.

The entire project has 5 main construction packages, with the total completed construction volume reaching 80%. However, package 13 from Km 2+190 to the intersection with Truong Chinh Street has been stalled for many months now. According to Giao Thong Newspaper reporters, the construction site is cluttered with machinery and equipment gathered but not in operation. At one point, there were only 3 workers working in the entire package. On the side adjacent to the residential area, the muddy and dirty road has made people's lives very inconvenient.

According to the Ho Chi Minh City Department of Transport, this package has reached about 65% of the total output, and has put a part of the road into temporary use, but is stalled due to lack of construction site. Specifically, this package is still stuck with 67 households and the area of ​​Textile Factory 7 blocking the route.

The Traffic Committee recommends that the city direct the Department of Planning and Architecture to promptly respond to the master plan of the 1/500 scale of the on-site resettlement land related to the project as requested by the People's Committee of Tan Binh District. From there, there will be a direction to resolve problems related to compensation and resettlement for households within the scope of the project.

To ensure the entire project opens to traffic in December 2024 to connect synchronously with Tan Son Nhat T3 terminal, the Traffic Committee proposed that the Ministry of National Defense direct the Military Region 7 Command to urgently hand over the area belonging to Textile Factory 7 to the People's Committee of Tan Binh District.

Image captures the entire view of package number 13 of the Tran Quoc Hoan - Cong Hoa connecting road project:
Một gói thầu thuộc dự án 4.800 tỷ qua sân bay Tân Sơn Nhất có nguy cơ

The entire row of houses within the project scope of package number 13 (Ward 13, Tan Binh District) is still blocking the middle of the road.

Một gói thầu thuộc dự án 4.800 tỷ qua sân bay Tân Sơn Nhất có nguy cơ

Grass grows green on the unfinished construction road.

Một gói thầu thuộc dự án 4.800 tỷ qua sân bay Tân Sơn Nhất có nguy cơ

Drainage system on a partially completed road. This area has become a place for people to cycle for exercise.

Một gói thầu thuộc dự án 4.800 tỷ qua sân bay Tân Sơn Nhất có nguy cơ

On the residential side, manhole covers and plastic pipes are scattered.

Một gói thầu thuộc dự án 4.800 tỷ qua sân bay Tân Sơn Nhất có nguy cơ

The concrete structure was filled with rainwater and the iron core was rusty.

Một gói thầu thuộc dự án 4.800 tỷ qua sân bay Tân Sơn Nhất có nguy cơ

Many people are impatient with the progress of package 13 due to the slow and stagnant construction.

Một gói thầu thuộc dự án 4.800 tỷ qua sân bay Tân Sơn Nhất có nguy cơ

The road was cleared many months ago but the investor could not construct it because of the electric pole.

Một gói thầu thuộc dự án 4.800 tỷ qua sân bay Tân Sơn Nhất có nguy cơ

The entire residential area has been disrupted for the past 6 months, but construction progress has not been able to speed up.

Một gói thầu thuộc dự án 4.800 tỷ qua sân bay Tân Sơn Nhất có nguy cơ

Instead of the urgent atmosphere of 3 shifts and 4 shifts, the final contract package of the road connecting Tran Quoc Hoan - Cong Hoa fell into a state of sluggish progress.

Một gói thầu thuộc dự án 4.800 tỷ qua sân bay Tân Sơn Nhất có nguy cơ

The construction camp area of ​​Package 13 was quiet over the past two weekends, with equipment lying in one place. Concrete structures and materials were scattered around.



Source: https://www.baogiaothong.vn/mot-goi-thau-thuoc-du-an-4800-ty-qua-san-bay-tan-son-nhat-co-nguy-co-gay-tien-do-192240930160847411.htm

Comment (0)

No data
No data

Same tag

Same category

Same author

No videos available