How are the key transport projects in Hanoi being implemented?

Báo Giao thôngBáo Giao thông29/07/2024


Specifically, at the Ring Road 4 project - Capital Region, localities have actively implemented and handed over the site for construction of the entire project. Up to this point, the total investment capital for the project is about 12,600 billion VND, the construction progress has reached 9.9% of the volume.

Loạt dự án giao thông trọng điểm tại Hà Nội đang triển khai đến đâu?- Ảnh 1.

The contractor is speeding up the progress of the Ring Road 4 section through Me Linh district. Photo: Ta Hai.

The project has basically completed the site clearance work, reaching about 98%, and the relocation of graves has reached nearly 98%. Currently, Hanoi has also completed all 13 resettlement areas, some localities have approved the land prices for departure and arrival, are arranging resettlement for households, and are constructing the relocation of high voltage power from 110kV to 500kV.

The contractors are continuing to speed up the construction of the parallel road. Up to now, many sections have been constructed to the crushed stone layer, the output to date has reached about 28% of the contract value.

The Ring Road 1 project, Hoang Cau - Voi Phuc section (phase 1) is 2.3km long, with a cross-section of 50m. The starting point of the route intersects with Cat Linh - La Thanh - Yen Lang road at Hoang Cau (Dong Da district) and the end point is at Voi Phuc intersection (Ba Dinh district). The investment level of phase 1 of the project is more than 7,200 billion VND from the city budget, of which the construction cost is 627 billion VND, the site clearance cost is 5,800 billion VND. To date, the project has disbursed 34.1% of the capital plan.

The project to improve and upgrade National Highway 6 from Ba La intersection (Ha Dong district) to Xuan Mai town (Chuong My district) is 21.7km long. This section will be upgraded to 4-6 lanes, designed speed of 80 km/h, roadbed width will be expanded to 50-60m, contributing to completing the radial axis connecting National Highway 21A, Ho Chi Minh road and Ring Road 4 - Capital Region. The total investment capital of the project is 8,100 billion VND from the city budget. To date, the project has disbursed 7.7% of the capital plan.

Thang Long Avenue Expressway, the section connecting National Highway 21 to Hanoi - Hoa Binh Expressway, is 6.7km long, with a cross-section of 120-180m. The total investment for the entire project is VND5,200 billion. To date, the project has disbursed 7.7% of the capital plan.



Source: https://www.baogiaothong.vn/loat-du-an-giao-thong-trong-diem-tai-ha-noi-dang-trien-khai-den-dau-192240729151457711.htm

Comment (0)

No data
No data

Same tag

Same category

Colorful Vietnamese landscapes through the lens of photographer Khanh Phan
Vietnam calls for peaceful resolution of conflict in Ukraine
Developing community tourism in Ha Giang: When endogenous culture acts as an economic "lever"
French father brings daughter back to Vietnam to find mother: Unbelievable DNA results after 1 day

Same author

Image

Heritage

Figure

Business

No videos available

News

Ministry - Branch

Local

Product