Installing thousands of glass panels on the roof of Long Thanh airport terminal

Việt NamViệt Nam20/12/2024

Currently, the passenger terminal contract with a total investment of 35,000 billion VND is constructing a steel roof structure and installing glass in completed areas.

According to Tri Thuc - Znews in mid-December, many items of Long Thanh International Airport (Dong Nai) are being urgently constructed by contractors despite the continuous drizzle.

Thousands of glass panels have been installed on the station's steel roof frame. Currently, the installation output of the station's steel roof structure has reached nearly 50%.

The Airports Corporation of Vietnam (ACV) said that the progress of the passenger terminal project is currently very fast, nearly a month ahead of schedule. The consortium of contractors has mobilized more than 3,000 workers and 1,000 pieces of equipment, focusing on the construction of the project's items.

Currently, the station has completed the entire reinforced concrete column and beam structure of the 4 floors.

The construction unit is completing the items of steel roof structure installation, construction of the telescopic bridge and processing, corridor stairs. The main roof steel frame structure alone has been processed, manufactured and painted to complete 17,450/28,240 tons.

About 12,694 tons of roof steel structures have been installed at the construction site, reaching nearly half of the output. Currently, the investor is urging and directing contractors to speed up the progress, especially the central roof section.

The steel roof structure is expected to be completed in July 2025, 5 months ahead of the contract schedule. The contractor will then complete the terminal roof in October 2025, 2 months ahead of the original schedule.

Dozens of large capacity cranes, weighing up to hundreds of tons, operate continuously to lift giant steel beams to the installation position.

The Long Thanh airport passenger terminal is considered the "heart" and is the critical path that determines the progress of the Long Thanh airport project phase 1. This package includes main items such as the construction of the passenger terminal, with a design including a central terminal and 3 wings, with a structure of 1 ground floor and 3 floors, the roof height reaches 45.55 m.

About 1 km away, the Long Thanh airport air traffic control tower has completed the rough construction, about 2 months ahead of schedule. After a year of construction, the Long Thanh airport air traffic control tower is in the stage of steel structure installation, finishing and electromechanical construction. The tower is at a height of 107.93 m, and was topped out on September 22.

The control tower is 123 m high and equipped with a radar on top of the tower, with a construction area of ​​about 80 m2, a tower body diameter of about 10 m, a control cabin at the airport with an area of ​​about 150 m2 and 2 parking control cabins with an area of ​​about 70 m2 each.

The project is designed in the shape of a lotus bud with a total investment of 3,500 billion VND. The Long Thanh airport air traffic control tower has colors and architectural structures that are in harmony with the passenger terminal and surrounding buildings.

Along with the air traffic control tower and passenger terminal, the construction of Long Thanh airport runway is also ahead of schedule. This package is expected to be completed by April 30, 2025.

Regarding the second runway, which has just been approved by the National Assembly for investment, Minister of Transport Tran Hong Minh requested the investor and related units to promptly implement procedures, and if necessary, appoint contractors with experience in constructing the first runway to shorten the progress and must be completed before December 31, 2025.

According to Znews