Revealing the names of investors in 8 Northern Expressway rest stop projects

Việt NamViệt Nam15/07/2024


Revealing the names of investors in 8 North-South expressway rest stop projects

Among the joint ventures of investors that won the bid for 8 investment projects to build and operate rest stops on the Eastern North-South Expressway, Petrolimex and Phuong Trang Passenger Transport Joint Stock Company were named the most times.

Illustration photo.
Illustration photo.

According to the Vietnam Expressway Administration, as of July 11, this unit has approved the results of selecting investors for 8 investment projects to build and operate rest stops on the Eastern North-South Expressway.

This is a group of rest stops belonging to the North-South Expressway component projects in the 2017-2020 period, which the Ministry of Transport is urgently completing the investment selection work to soon begin construction.

The investment project to build and operate the Km47+500 rest stop under the Phan Thiet – Dau Giay component project has the winning investor being the Futabuslines – Thanh Hiep Phat Joint Venture (the Joint Venture of Phuong Trang Passenger Transport Joint Stock Company – Thanh Hiep Phat Company Limited) with the value in money paid to the state budget of 260 billion VND; the preliminary value of the project implementation cost is 290.716 billion VND; the value of compensation, support and resettlement is 3.342 billion VND.

The overall progress of the Project is 15 months, of which the completion time for public service works is 12 months; the project exploitation time after completing the investment work is 25 years.

The investment project to build and operate the Km329+700 rest stop under the Mai Son - National Highway 45 component project has the winning investor being the Petrolimex Joint Venture (Vietnam National Petroleum Group Joint Venture) - Thua Thien Hue Petroleum Company; the value in money paid to the state budget is 111 billion VND; the preliminary value of the project implementation cost is 201.685 billion VND; the value of compensation, support and resettlement is 10.454 billion VND.

The overall progress of the Mai Son - National Highway 45 Rest Stop Project is 17 months, of which the time to complete public service works is 11 months. The project exploitation time after completing the investment work is 25 years.

The investment project to build and operate the Km144+560 rest stop under the Vinh Hao – Phan Thiet component project has the winning investor being the Futabuslines – Thanh Hiep Phat Joint Venture; the value in money paid to the state budget in this project is 140 billion VND; the preliminary value of the project implementation cost is 313.441 billion VND; the value of compensation, support and resettlement is 33.997 billion VND.

Overall project progress is 15 months, of which the time to complete public service works is 12 months; the project exploitation time after completing the investment work is 25 years.

The project to invest in the construction and operation of the Km90+900 rest stop under the Cam Lam – Vinh Hao component project on the North – South Eastern expressway has the winning investor being the Futabuslines – Thanh Hiep Phat Joint Venture; the value in money paid to the state budget is 140 billion VND; the preliminary value of the project implementation cost is 299.812 billion VND; the value of compensation, support and resettlement is 14.454 billion VND.

The overall progress of the Project is also 15 months, of which the completion time for public service works is 12 months; the project exploitation time after completing the investment work is 25 years.

The project to invest in the construction and operation of the Km205+092 rest stop under the Vinh Hao – Phan Thiet component project has the winning investor being the Thanh Thanh Nam – Chau Thanh – Viet Han – Saigon Investment – ​​Thanh Thanh Cong Lam Dong Joint Venture (Joint Venture of Thanh Thanh Nam Joint Stock Company – Chau Thanh Petroleum Service Trading Company Limited – Viet Han Automobile Joint Stock Company – Saigon Investment Investment and Development Joint Stock Company – Thanh Thanh Cong Lam Dong Tourism Company Limited). The winning bid price for this project includes the value in cash paid to the state budget of VND 81,009 billion; the preliminary value of the project implementation cost is VND 316,491 billion; the value of compensation, support, and resettlement is VND 36,37 billion.

The overall project schedule is 18 months, of which the completion time for public service works is 12 months; the project exploitation time after completing the investment work is 25 years.

The investment project to build and operate the Km33+930 Rest Stop under the Nha Trang – Cam Lam Component Project has the winning investor being the Petrolimex – Thua Thien Hue Petroleum Company consortium with the value in money paid to the state budget of 107.1 billion VND; the preliminary value of the project implementation cost is 202.828 billion VND; the value of compensation, support and resettlement is 20.448 billion VND.

The overall project schedule is 17 months, of which the completion time for public service works is 11 months. The project exploitation period after completing the investment is 25 years.

The investment project to build and operate the rest stop Km427+035 under the Nghi Son – Dien Chau component project has the winning investor being the consortium of Petrolimex – Thua Thien Hue Petroleum Company. The value in money paid to the state budget for this project is 86 billion VND; the preliminary value of the project implementation cost is 196.397 billion VND; the value of compensation, support and resettlement is 16.743 billion VND.

This project has an overall progress of 17 months, of which the time to complete public service works is 11 months. The project exploitation time after completing the investment work is 25 years.

The investment project to build and operate the Km478+200 Rest Stop under the Dien Chau – Bai Vot component project on the North – South Eastern Expressway has the winning investor being the consortium of Petrolimex – Thua Thien Hue Petroleum Company with the value in money paid to the State budget of 50 billion VND; the preliminary value of the project implementation cost is 218.7 billion VND; the value of compensation, support and resettlement is 15.28 billion VND.

Overall project progress is 17 months, of which the time to complete public service works is 11 months; project exploitation time after completing investment work: 25 years.

These projects all have construction items including: public service works, providing free services (parking lots, resting spaces, temporary rest rooms for drivers, toilets, information provision areas, places to organize and launch traffic safety propaganda, places for rescue workers, first aid for traffic accidents); commercial service works (food and beverage service areas, areas for introducing and selling goods, fuel stations, electric vehicle charging stations, vehicle maintenance and repair workshops, car washes; restaurants, entertainment areas, other essential services to meet people's needs); auxiliary works that are symbols of the locality or of rest stops.

When put into operation, the projects will create more necessary amenities and contribute to improving traffic safety on the North-South expressway in the East.

Mr. Lam Van Hoang, Director of the Vietnam Expressway Administration, said that relevant agencies are currently speeding up negotiations with investors with the hope of shortening construction time, striving to sign contracts for 8 rest stop projects in July 2024.

Source: https://baodautu.vn/he-lo-ten-tuoi-nha-dau-tu-8-du-an-tram-dung-nghi-cao-toc-bac—nam-d219755.html


Comment (0)

No data
No data

Same tag

Same category

Son Doong Cave is among the top 'surreal' destinations like on another planet
Wind power field in Ninh Thuan: Check-in "coordinates" for summer hearts
Legend of Father Elephant Rock and Mother Elephant Rock in Dak Lak
View of Nha Trang beach city from above

Same author

Heritage

Figure

Business

No videos available

News

Political System

Local

Product