On the morning of July 13, comrade Le Duc Giang, member of the Provincial Party Committee, Vice Chairman of the People's Committee of Thanh Hoa province chaired a conference to review and resolve difficulties and problems in the implementation of the Compensation and Resettlement Support Component in Nhu Xuan district of the Ban Mong Reservoir Project, Phase 1, Nghe An province.
Vice Chairman of the Provincial People's Committee Le Duc Giang chaired the conference.
The Ban Mong Reservoir Project Phase 1, Nghe An Province was approved by the Prime Minister to adjust the investment policy in Decision No. 1248/QD-TTg dated October 26, 2023; The Minister of Agriculture and Rural Development (MARD) approved the adjustment of the investment project in Decision No. 532/QD-BNN-XD dated February 7, 2024. In particular, the work contents and funding for the implementation of the Compensation, Support and Resettlement Component in Nhu Xuan District, Thanh Hoa Province with a total estimated cost of nearly 517 billion VND were added, the Department of Agriculture and Rural Development of Thanh Hoa was assigned as the investor of the Component.
Director of the Department of Agriculture and Rural Development Cao Van Cuong reported at the conference.
Secretary of Nhu Xuan District Party Committee Luong Thi Hoa spoke at the conference.
The main contents of this Component include: Compensation, support; investment in construction of resettlement areas and afforestation to replace the forest area that must change its purpose of use to implement the project in Nhu Xuan district, ensuring the progress of handing over the reservoir area to elevation (+71.86m) before October 30, 2024, handing over the entire reservoir area before July 31, 2025 and completing the entire project no later than December 31, 2025.
Leaders of the Department of Natural Resources and Environment spoke at the conference.
Up to now, the Department of Agriculture and Rural Development has completed the following tasks: The competent authority has approved the policy of changing the purpose of forest use, the plan for reforestation and completed the payment and disbursement of the fund for reforestation in Thanh Hoa province of more than 184.6 billion VND; agreed on the location of the resettlement area with the Vietnam Rubber Industry Group; extracted the cadastral map of the reservoir area (up to cos + 76.4m) and the resettlement area; surveyed and made a detailed construction plan at a scale of 1/500 for the resettlement area; completed the survey and made a project for investment in the Component; completed a number of other consulting packages as approved by the Ministry of Agriculture and Rural Development.
Director of Thanh Hoa Agricultural and Rural Development Construction Investment Project Management Board spoke at the conference.
However, during the implementation process, there are still some related problems, such as: Regarding the irrigation land target with the need to implement the project in Thanh Hoa province is 681.28 ha. However, up to now, only 382.64 ha (corresponding to the elevation of +71.86m in the reservoir area) has been allocated. The remaining area of 298.64 ha of irrigation land (from elevation of +71.86m to elevation of +76.4m in the reservoir area) has not been allocated yet. In addition, there are some other difficulties and problems related to the appraisal and approval of the contents of the Compensation, Support and Resettlement Components...
Vice Chairman of the Provincial People's Committee Le Duc Giang delivered a concluding speech at the conference.
After listening to the opinions of departments, branches and Nhu Xuan district, Vice Chairman of the Provincial People's Committee Le Duc Giang assigned the Department of Agriculture and Rural Development to take full responsibility for the project's progress, assign staff to coordinate with relevant units to implement the project, and report the progress to the Provincial People's Committee weekly.
The Department of Natural Resources and Environment urgently reports to the Provincial People's Committee to arrange irrigation land to ensure an area of 298.64 hectares, transferred from localities and units but not affecting the economic development of localities and not disrupting the situation, reporting before July 22, 2024.
The People's Committee of Nhu Xuan district established a Steering Committee to carry out compensation and site clearance tasks, and report progress weekly to the Provincial People's Committee through the Department of Agriculture and Rural Development.
The Department of Natural Resources and Environment assigned staff to coordinate with the People's Committee of Nhu Xuan district to carry out compensation and site clearance work, ensuring that people who give up land for the project have a stable life, better than their old place of residence.
The Department of Agriculture and Rural Development coordinates with the Department of Construction Management (Ministry of Agriculture and Rural Development) to urgently advise the Ministry of Agriculture and Rural Development to change Decision No. 532/QD-BNN-XD dated February 7, 2024, including components of reforestation, compensation support, and resettlement area construction, especially technical and land parameters, as a basis for compensation implementation.
Vice Chairman of the Provincial People's Committee Le Duc Giang also sincerely thanked the Vietnam Rubber Industry Group for actively coordinating with Thanh Hoa province, creating conditions to cede the Group's land so that the province could arrange a resettlement area for people affected by the Ban Mong Reservoir Project Phase 1.
Le Hoi