On the afternoon of June 3, comrade Nguyen Van Thi, member of the Provincial Party Standing Committee, Permanent Vice Chairman of the Provincial People's Committee chaired a conference to listen to a report on the implementation status and resolve difficulties and problems of Project No. 1 - Duc Giang Nghi Son Chemical Complex in Nghi Son Economic Zone.
Conference overview.
Attending the conference were comrade Nguyen Tien Hieu, member of the Provincial Party Standing Committee, Head of the Management Board of Nghi Son Economic Zone and Provincial Industrial Parks.
Delegates attending the conference.
According to the report, Project No. 1 - Duc Giang Nghi Son Chemical Complex was approved by the Provincial People's Committee Chairman in Decision No. 2152/QD-UBND dated June 11, 2020 by Duc Giang Nghi Son Chemical Company Limited as the investor; with a capacity of 151,000 tons of chemicals/year, located in Tan Truong and Tung Lam communes (Nghi Son town), land area of 30 hectares. Total investment capital is VND 2,400 billion, of which the investor's capital contribution is 40%, mobilized capital is 60%. The project progress according to the Investment Registration Certificate is to start construction in June 2021 and complete in December 2022.
Delegates attending the conference.
Up to now, the investor has coordinated with the Nghi Son Town People's Committee to complete the compensation and site clearance for the entire 30 hectares of the project. The investor has leveled 22.3 hectares/30 hectares; deployed geological exploration drilling, completed 177 drills to serve the work of preparing the factory design documents. In addition, the company has also completed a number of other related legal procedures.
Delegates speak at the conference.
However, up to now, the project still has some problems in completing the fire prevention and fighting records. The project belongs to industrial zone No. 15, but currently industrial zone No. 15 has not been approved for the construction zoning plan at a scale of 1/2000, so there is no traffic connection location, water supply and drainage close to the project boundary. Therefore, there is not enough basis for the Ministry of Industry and Trade to appraise the feasibility study report. In addition, the project of moving, arranging residents, and resettling some households in Lam Quang village, Tan Truong commune (Nghi Son town) has not been completed, affecting the implementation of some construction items of the project.
Comrade Nguyen Tien Hieu, Member of the Provincial Party Standing Committee, Head of the Management Board of Nghi Son Economic Zone and provincial industrial parks spoke at the conference.
After listening to the reports and opinions of the sectors at the conference, Permanent Vice Chairman of the Provincial People's Committee Nguyen Van Thi highly appreciated the efforts of the investor as well as related sectors, units and localities throughout the project implementation process.
With the difficulties and obstacles of the project, he requested the Provincial People's Committee Office to absorb the opinions at the conference to submit to the Provincial People's Committee to issue a notice assigning tasks to relevant agencies and units in the coordination work to complete the project's documents and procedures.
Permanent Vice Chairman of the Provincial People's Committee Nguyen Van Thi delivered a concluding speech at the conference.
The Management Board of Nghi Son Economic Zone and Industrial Zones receives the company's documents to carry out land allocation in accordance with the provisions of law. Accordingly, within 5 days of receiving the company's documents, the leaders of the Management Board of Nghi Son Economic Zone and Industrial Zones direct relevant departments to advise on land lease procedures. At the same time, within 5 days, after receiving the documents from the Management Board of Nghi Son Economic Zone and Industrial Zones, the Department of Natural Resources and Environment must submit them to the Provincial People's Committee for consideration, appraisal and approval to assign the Management Board of Nghi Son Economic Zone and Industrial Zones to decide on land lease.
Delegates attending the conference.
The Management Board of Nghi Son Economic Zone and industrial zones continues to study legal regulations related to investment adjustment dossiers. Along with that, the company needs to complete procedures in case of adjustment.
The authorities continue to pay attention and support the company in completing investment procedures, as well as related legal aspects. Nghi Son town speeds up the investment progress of resettlement projects for affected people.
Conference overview.
Duc Giang Nghi Son Chemical Company Limited must complete procedures related to fire prevention and fighting issues based on submission to central ministries and branches, and strive to complete them in the third quarter of 2024. At the same time, continue to research and expand investment, as well as coordinate with departments, branches, and localities to complete the remaining procedures; prepare conditions according to the provisions of law to start the project in the third quarter of 2024. In addition, the company must work with related units to ensure plans for electricity and water supply during the project's commencement and operation...