On May 20, at the section from Ba La intersection to Xuan Mai town, Giao Thong Newspaper reporters recorded that the construction atmosphere was quite gloomy. Only a few workers were working on the section through Phu Nghia and Tien Phuong communes (Chuong My district) with a length of about 3km/a total of more than 21km. The remaining sections do not have machinery or workers (In the photo, only Tan Truong bridge is being constructed by workers on the bridge piers, the remaining bridges are still in a state of immobility such as: Mai Linh, Dong Tru, Quan Lat, Xuan Mai, Song Bui, Nam Lu).
Source: https://www.baogiaothong.vn/du-an-mo-rong-ql6-di-xuan-mai-sau-hon-15-nam-thi-cong-192240520170413027.htm