Nhon Urban Railway Project

Báo Tiền PhongBáo Tiền Phong30/07/2024


TPO - July 28 is the deadline for commercial operation, but up to now, the Nhon - Hanoi Railway Station elevated section (from Nhon Station to Cau Giay) urban railway project is still "inactive", not welcoming passengers as planned.

Nhon - Hanoi Railway Station metro project continues to miss deadlines

Nhon - Hanoi Railway Station Urban Railway Project Misses Its 14th Deadline Photo 1

Regarding the Nhon - Hanoi Railway Station urban railway line, recently, Deputy Prime Minister Tran Hong Ha requested the Hanoi People's Committee to be responsible for directing relevant agencies and units to urgently complete tasks, contents and procedures such as coordinating with agencies of the Ministry of Transport to complete the appraisal and issuance of System Safety Certificates according to regulations; environmental licensing procedures on July 20.

Nhon - Hanoi Railway Station Urban Railway Project Misses Its 14th Deadline Photo 2
The Deputy Prime Minister also requested to complete the procedures for inspecting and accepting the project before July 26, 2024, ensuring the Nhon - Hanoi Railway Station elevated section is put into commercial operation before July 28, and the completion schedule must not be delayed.
Nhon - Hanoi Railway Station Urban Railway Project Misses Its 14th Deadline Photo 3
However, as of July 30, the Nhon - Hanoi Railway Station metro project is still "inactive", showing no signs of operation.
Nhon - Hanoi Railway Station Urban Railway Project Misses Its 14th Deadline Photo 4Nhon - Hanoi Railway Station Urban Railway Project Misses Its 14th Deadline Photo 5

It has been noted that in recent days, the elevated stations of this railway line remain closed.

Nhon - Hanoi Railway Station Urban Railway Project Misses Its 14th Deadline Photo 6

The entrance to Le Duc Tho station is protected by barbed wire fences, and the elevators are covered with tarpaulins.

Nhon - Hanoi Railway Station Urban Railway Project Misses Its 14th Deadline Photo 7Nhon - Hanoi Railway Station Urban Railway Project Misses Its 14th Deadline Photo 8Nhon - Hanoi Railway Station Urban Railway Project Misses Its 14th Deadline Photo 9Nhon - Hanoi Railway Station Urban Railway Project Misses Its 14th Deadline Photo 10

At Cau Dien station, after heavy rains, the shabby scene reappears.

Nhon - Hanoi Railway Station Urban Railway Project Misses Its 14th Deadline Photo 11
The train station corridor was occupied by people to store goods.
Nhon - Hanoi Railway Station Urban Railway Project Misses Its 14th Deadline Photo 12

Up to now, the construction progress of the elevated section of the Nhon - Hanoi Railway Station metro line has reached 100% of the volume. Currently, 10 trains of the project have completed the test run and have been granted license plates by the Vietnam Register for operation. However, the project is currently being evaluated, appraised and accepted by specialized agencies, so the trains can only operate after this work is completed.

Referee



Source: https://tienphong.vn/du-an-duong-sat-do-thi-nhon-ga-ha-noi-lo-hen-lan-thu-14-post1659324.tpo

Comment (0)

No data
No data

Same tag

Same category

When community tourism becomes a new rhythm of life on Tam Giang lagoon
Ninh Binh tourist attractions not to be missed
Wandering in the clouds of Dalat
Villages on the Truong Son mountain range

Same author

Heritage

Figure

Business

No videos available

News

Political System

Local

Product