DNVN - At 4:34 p.m. on December 7, Dong Nai Hydropower Company produced 1,377 million kWh, completing the electricity output target (23 days ahead of schedule) compared to the 2024 plan assigned by Power Generation Corporation 1 (EVNGENCO1).
In 2024, Dong Nai Hydropower Company has proactively monitored the hydrological situation and rainfall in the reservoir basin to calculate, closely coordinate and regularly inform the Disaster Prevention and Search and Rescue Committee of Dak Nong and Lam Dong provinces. Together with related units, propose optimal power generation operation plans for generators, while regulating the reservoir, ensuring safety for downstream areas in the most effective rainy season.
Dong Nai Hydropower Company completed the 2024 electricity production target 23 days ahead of schedule.
The company has also closely coordinated with the National Electricity System and Market Operation Company Limited (NSMO) and coordinated well with localities to use water resources effectively to ensure irrigation and domestic water according to the needs of the downstream, meeting the inter-reservoir process in the Dong Nai river basin.
With the efforts of the Board of Directors and all staff, Dong Nai Hydropower Company officially reached the milestone of 1,377 million kWh at 4:34 p.m. on December 7, 2024, completing the electricity output target assigned by Power Generation Corporation 1.
On-duty shift to operate and monitor generator equipment.
According to Mr. Nguyen Quang Vinh - Party Secretary, Director of Dong Nai Hydropower Company, to achieve this result, from the beginning of the year, the Company has established monthly and yearly operation plans for 2024; focusing on improving the availability and readiness of generators of Dong Nai 3 and Dong Nai 4 Hydropower Plants.
At the same time, strictly control economic and technical indicators; effectively implement operation, repair, maintenance and promote emulation in production labor, enhance digitalization of technological equipment, ensure safe and reliable operation of machines, equipment systems, and works.
Dong Nai 4 Hydropower Reservoir.
In addition, other economic and technical indicators, such as: self-consumption electricity rate; availability coefficient; breakdown shutdown rate; maintenance and repair shutdown rate of the company up to now have all reached and exceeded the plan, contributing significantly to the socio-economic development of the two provinces of Lam Dong and Dak Nong and supplying electricity to the national grid system.
According to Mr. Nguyen Quang Vinh, it is expected that by December 31, 2024, Dong Nai Hydropower Company will continue to produce about 40 million kWh of electricity and reach a total electricity output of about 1,417 billion kWh in the year (103% of the 2024 plan).
Officers, workers and employees of Dong Nai Hydropower Company contributed to support people in the Northern provinces to overcome the consequences caused by storm No. 3 (storm Yagi).
At the same time, continue to orient the implementation of production and business tasks to ensure "safe, flexible and effective adaptation" and implement solutions to increase cost reduction and improve the efficiency of production and business activities...
“In parallel with completing the electricity output target, in 2024, the Company has carried out social security activities well to enhance the role and responsibility of Dong Nai Hydropower Company in particular and Power Generation Corporation 1 in general towards the community”, Mr. Nguyen Quang Vinh shared.
Yuan You