There is still a "football" situation when dismantling renewable energy projects.

Việt NamViệt Nam16/04/2025


Deputy Prime Minister: There is still a situation of 'playing football' up and down when dismantling renewable energy projects - Photo 1.
Permanent Deputy Prime Minister Nguyen Hoa Binh chaired the meeting.

On the afternoon of April 15, Permanent Deputy Prime Minister Nguyen Hoa Binh made this assessment when chairing a combined online and in-person meeting of Steering Committee 751 with leaders of several ministries, branches, and localities on removing difficulties and obstacles for renewable energy projects.

Many local problems

The meeting listened to and reviewed the report of the Ministry of Industry and Trade on the implementation of the plan to implement Resolution No. 233 dated December 10, 2024 of the Government on removing obstacles and difficulties for renewable energy projects.

According to Deputy Minister of Industry and Trade Nguyen Hoang Long, the Ministry of Industry and Trade has sent documents to the People's Committees of provinces with renewable energy projects and Vietnam Electricity Group (EVN) to urge the implementation of the plan and proactively resolve problems and difficulties of the projects.

The Ministry also has a report summarizing the implementation results of Resolution No. 233, including some localities that have not yet reported, some localities and EVN have reported but not fully, specifically on the results of resolving problems according to authority.

At the same time, many localities such as Dak Lak, Quang Binh, Ninh Thuan, Binh Thuan, Dak Nong, Quang Nam, Binh Duong, etc. have had specific reports on handling difficulties, problems and existing problems that need to be focused on handling and resolving.

For example: Procedures related to land; acceptance of construction works; enjoying preferential prices (FIT); handling difficulties for rooftop solar power projects;...

The Ministry of Industry and Trade recommends that the Government and the Steering Committee pay attention to and direct the project's removal. EVN actively resolves difficulties and obstacles within its authority. Completes early, reports results according to regulations and is responsible to the Government and Government leaders for any delay in reporting.

Regarding the conversion of forest and forest land use purposes, it is necessary to completely resolve the problems according to regulations. Solve the problems of agricultural and forestry land of large-scale rooftop solar power projects built on agricultural and forestry land under the model of investment in farming and aquaculture.

EVN urgently resolves problems and reports on implementation results of renewable energy projects enjoying FIT prices and large-scale rooftop solar power projects built on agricultural and forestry land under the model of farm investment.

Relevant localities urgently coordinate with EVN and electricity companies to provide information on large-scale rooftop solar power projects built on agricultural and forestry land under the model of farm investment for consideration and handling.

Localities seriously learn from experience

In conclusion, Permanent Deputy Prime Minister Nguyen Hoa Binh emphasized that in the context of the complicated and unpredictable developments in the international and regional economic situation, we must face many difficulties and challenges and resolutely achieve the growth target of at least 8% in 2025 and double digits in the following years. Therefore, promoting public investment disbursement and removing difficulties for projects is a task of special importance.

Welcoming the localities that, following the direction, have urgently focused on removing difficulties and obstacles for renewable energy projects so that the projects can continue to be implemented and put into operation, Mr. Binh said that there are still localities that have not actively removed difficulties and have not fulfilled their responsibilities, and there is still a situation of "kicking the ball up and down", these localities need to seriously learn from their experiences.

Accordingly, he requested that the parties continue to review the difficulties and obstacles for energy projects to remove them for businesses. Especially the contents related to the order of construction and licensing procedures; issues related to planning; conversion of land use purposes; preferential prices (FIT);...

All these problems need to be focused on and implemented in May 2025 with the spirit that the difficulties and problems of any level, ministry, sector, or locality must be considered, handled, and resolved by the units.



Source: https://baodaknong.vn/con-tinh-trang-da-bong-khi-thao-go-du-an-nang-luong-tai-tao-249521.html

Comment (0)

No data
No data

Same tag

Same category

Discover Mu Cang Chai terraced fields in the flooding season
Fascinated by birds that lure mates with food
What do you need to prepare when traveling to Sapa in the summer?
The wild beauty and mysterious story of Vi Rong cape in Binh Dinh

Same author

Heritage

Figure

Business

No videos available

News

Political System

Local

Product