Cam Pha: Focus on completing the extended coastal road

Việt NamViệt Nam16/01/2025

The project of the road connecting Vung Duc Street, Cam Dong Ward to Cam Son Ward, Phase I, is synchronously connected with the coastal road of Ha Long - Cam Pha. Immediately after receiving the source of filled soil coordinated according to the circular plan from the National Highway 279 Renovation and Upgrading Project, the investor and contractors have focused on human resources, increased construction teams and strived to complete the project in early 2025. The project, when put into use, will contribute to expanding the development space of Cam Pha City. At the same time, it lays the foundation for the synchronous implementation of the coastal road of Bai Tu Long Bay in Cam Pha City.

The project of the road connecting Vung Duc street, Cam Dong ward to Cam Son ward connects directly and synchronously with the Ha Long - Cam Pha coastal road.
The project of the road connecting Vung Duc street, Cam Dong ward to Cam Son ward connects directly and synchronously with the Ha Long - Cam Pha coastal road.
After nearly 1 month of coordinating the source of fill soil, the project has completed the K95 and K98 roadbed layers.
After nearly 1 month of coordinating the source of fill soil, the project has completed the K95 and K98 roadbed layers.
The seawall project to protect the environment has been completed.
The sea dike project to protect the environment has been completed.
Contractors focus on constructing sidewalks and median strips.
Contractors focus on constructing sidewalks and median strips.
The construction atmosphere is bustling in the days before the Lunar New Year of At Ty, striving to complete 2 layers of crushed stone to organize asphalt paving in the first days of the new year.
The construction atmosphere is bustling in the days before the Lunar New Year of At Ty, striving to complete 2 layers of crushed stone to organize asphalt paving in the first days of the new year.
The completion of the project will be the premise for Cam Pha to deploy the next phases and complete the entire coastal road along Bai Tu Long Bay.
The completion of the project will be the premise for Cam Pha to balance resources to deploy the next phases and complete the entire coastal road along Bai Tu Long Bay.

Source

Comment (0)

No data
No data

Same tag

Same category

Wandering around Lach Bang beach village
Explore Tuy Phong color palette
Hue - The capital of the five-panel ao dai
Colorful Vietnamese landscapes through the lens of photographer Khanh Phan

Same author

Heritage

Figure

Business

No videos available

News

Ministry - Branch

Local

Product