At the conference summarizing the investment and construction work of the 500kV transmission line (DZ) circuit 3 project from Quang Trach (Quang Binh) to Pho Noi (Hung Yen) held on the morning of December 8, Vietnam Electricity Group (EVN) drew 6 valuable lessons.
If the 500kV line 1 was invested and built with the spirit of daring to do and taking responsibility, the 500kV line 2 was built with the spirit of promoting internal strength and national self-reliance, then the 500kV line 3 project was built with the spirit of promoting the combined strength of the entire political system from the Government, ministries, branches, local authorities at all levels, and people who joined hands and unanimously overcame all difficulties and innovated ways of working to bring the project to the finish line on schedule.
The Prime Minister visited and encouraged construction workers in Thanh Hoa. Photo: TL.
The Prime Minister has repeatedly emphasized: “Resources come from thinking and vision, motivation comes from innovation and creativity, strength comes from people and businesses”.
From the success of the Circuit 3 Projects, EVN has learned many valuable lessons:
The first is the lesson on leadership and direction. The Projects received the attention and strong direction of the Prime Minister, Deputy Prime Ministers, the State Steering Committee for important national programs, works and projects, key energy sector (Steering Committee), the Ministry of Industry and Trade, the State Capital Management Committee at Enterprises, and the participation of local authorities at all levels.
Second , management, operation and implementation. Right from the beginning of the project implementation, the Prime Minister directed: "The ideology must be clear. The determination must be high, the effort must be great, the action must be drastic, with focus, key points, each task must be completed, the assignment must be clear to the person, the task, the responsibility, the time, the product, the result, easy to check, urge and evaluate". Every month, the Prime Minister and Deputy Prime Minister directly meet to check the progress and assign specific tasks to the units. The State Steering Committee for important national programs, works and projects, in the energy sector, holds regular meetings every 2 weeks under the chairmanship of the Standing Deputy Head, Minister of Industry and Trade. From there, obstacles have been promptly removed, responsibilities and time for resolution have been clearly defined to promote progress.
The Minister of Industry and Trade, the European - American Market Department, the Asian - African Market Department, and trade offices in Russia, China, and India actively resolved related problems for imported shipments. The Ministry of Finance and the General Department of Customs directed to create the best conditions for imported materials and equipment to be cleared as quickly as possible. The Ministry of Transport directed to approve the plan to pull cables across roads and rivers as quickly as possible, and directed transport units to prioritize the transportation of goods and materials for the project.
Leaders of the Ministry of Industry and Trade, the State Capital Management Committee at Enterprises, the Party Committee of the Central Enterprises Bloc, and the Vietnam General Confederation of Labor regularly inspect and encourage workers at construction sites. Leaders of the Provincial Party Committee and the People's Committee resolutely direct departments, branches, and localities to speed up the progress of compensation and site clearance. Leaders of EVN/EVNNPT and Project Management Boards are always present at construction sites and factories to urge the construction progress and the progress of supplying materials and equipment. Consulting contractors for design, manufacturing steel columns, and construction contractors arrange competent leaders to be on duty at construction sites and factories to command each team/team/group, promptly remove obstacles, and ensure the required progress.
500kV line 3 passes through Nga Son district (Thanh Hoa).
Third , is the participation of authorities at all levels and the consensus of local people. Accordingly, implementing the Prime Minister's direction on "4 on-site", local people and businesses participate in providing materials, construction machinery, and participating in the construction of items suitable to their capacity.
...projects mobilized in localities: 2,267 construction machines of all kinds, accounting for 92% of total construction machines: 7,273 people, accounting for 90% of unskilled labor; purchased construction materials from 226 companies, accounting for 95% of total volume. |
As a result, the projects mobilized in the localities: 2,267 construction machines of all kinds, accounting for 92% of the total number of construction machines; 7,273 people, accounting for 90% of unskilled labor; purchased construction materials from 226 companies, accounting for 95% of the total volume. The good implementation of the "4 on-site" work made the interests of the people and businesses harmonious, the project progress was accelerated, the people in the localities understood the importance of the project, supported the project, gave up their housing and production land for construction, making the site clearance work accelerated and no complaints occurred.
The Thanh Hoa 500kV Transformer Station project and connecting lines were completed and energized on June 28. Photo: TL.
Fourth , the efforts, joint efforts, and solidarity of all forces participating in the construction. Steel column suppliers and construction contractors have focused all resources and efforts with the investor to overcome all difficulties, organize production and construction in "3 shifts and 4 teams", "overcome the sun, overcome the rain", "through holidays, Tet, and days off", ensuring progress, quality, and requirements.
EVN/EVNNPT promoted all its endogenous strength and the spirit of "only talking about doing, not thinking about retreating", mobilizing more than 3,300 cadres and workers in units of the Electricity industry across the country to volunteer to participate in supporting the construction of projects. |
EVN/EVNNPT has promoted all its internal strength and the spirit of "only discussing, not retreating", mobilizing more than 3,300 cadres and workers in units of the Electricity sector across the country to volunteer to participate in supporting the construction of projects. The determination, full effort and results achieved in the construction of the 500kV DZ Circuit 3 Projects of EVN/EVNNPT have been commended by the Prime Minister, recognized by the Government, Ministries, localities and people, contributing to enhancing the image of electricians, the image of the Vietnam Electricity sector always striving and dedicating itself to the electricity for the country and the people.
Viettel, PVN and VNPT Groups joined forces to send 12 teams with nearly 250 people to participate in erecting the poles. Vietnam Railway Corporation promptly transported nearly 1,000 containers of imported materials and equipment to hand over to construction units. Military Region IV sent more than 1,000 officers and soldiers to support the transportation of materials and equipment, and pulling wires at difficult construction sites. |
Promoting the combined strength of the Army, People's Public Security, Fatherland Front, State-owned corporations, the Central Committee of the Ho Chi Minh Communist Youth Union, and local Women's Unions, together with EVN/EVNNPT and contractors, have closely and effectively coordinated and cooperated in accordance with the spirit of "unanimity from top to bottom, smooth operation throughout". Viettel, PVN and VNPT Groups have joined forces to send 12 teams with nearly 250 people to participate in erecting the poles. Vietnam Railways Corporation has promptly transported nearly 1,000 containers of imported materials and equipment to hand over to construction units. Military Region IV has sent more than 1,000 officers and soldiers to support the transportation of materials and equipment, and pulling wires at difficult construction sites. The police force regularly stays close to the construction site to ensure security and order. The Central Committee of the Ho Chi Minh Communist Youth Union and the Youth Unions of 09 provinces have promoted the spirit of "wherever needed, there are youth, where there are difficulties, there are youth", mobilizing 465 teams with 6,272 young volunteers to participate at 297 construction sites, supporting people to dismantle and relocate houses, transport materials and equipment, and ensure traffic safety.
Officers and soldiers of Regiment 3, Division 324 (Military Region 4) and officers and soldiers of Thanh Hoa Provincial Military Command participated in supporting wire pulling at the construction area of Phu Son commune (Nghi Son town).
Fifth , the important role of communication work. Thanks to good propaganda work, local people understand the importance of the project and always agree and support the projects. Central and local television and press agencies have not been afraid of harsh weather and difficult terrain, promptly present at the construction site to record and report, creating many articles and films with many beautiful images that move people's hearts about the cadres, engineers, and workers who are working hard on the construction site, contributing to encouraging, motivating and spreading the inspiration of enthusiastic work to other important and key projects of the country.
From the time the Project was started until its completion and energization, more than 6,600 news articles were published on various media such as local national television, electronic newspapers, print newspapers, and social networks, attracting the attention and interaction of millions of viewers and readers across the country.
Sixth , promote the role of the Trade Union in emulation work, encourage the spirit of enthusiastic work. The Vietnam General Confederation of Labor and the Vietnam Electricity Trade Union have regularly visited, given gifts, encouraged workers, and encouraged the spirit of enthusiastic work at the construction site. Launched a summary of many emulation movements such as: "Fastest progress; Best quality; Most safe and economical; Most creative: Best care for life"; Sprint emulation campaign "45 days and nights to complete the 500 kV Line 3 Projects from Quang Trach - Pho Noi"... The movements were enthusiastically responded by investors, contractors, steel pole manufacturers and related units with about 30,000 workers, creating motivation and determination to complete the projects on schedule.
Minh Hieu