11 renewable energy projects have generated commercial electricity to the grid

VTC NewsVTC News27/06/2023


On the morning of June 27, Mr. Tran Viet Hoa, Director of the Electricity Regulatory Authority (Ministry of Industry and Trade) informed VTC News that by the end of June 26, 70/85 transitional renewable energy projects with a total capacity of 3,851.86 MW had sent documents to the Electricity Trading Company to negotiate electricity prices and power purchase contracts; 11 factories/parts of factories with a total capacity of 545.72 MW had completed COD procedures and were able to generate commercial electricity to the grid; 24 projects were under trial operation.

The cumulative electricity output of transitional renewable energy projects reached about 59.47 million kWh; of which, the average daily electricity output was about 3.2 million kWh, accounting for about 0.4% of the total mobilized electricity output.

There are 11 renewable energy plants qualified to connect to the national grid. (Illustration photo: Government Newspaper).

There are 11 renewable energy plants qualified to connect to the national grid. (Illustration photo: Government Newspaper).

In addition, 59 projects (total capacity of 3,211.41 MW) have proposed provisional prices equal to 50% of the ceiling price of the price range (according to Decision No. 21/QD-BCT dated January 7, 2023 of the Ministry of Industry and Trade). EVN and investors have completed price negotiations and initialed PPA contracts with 55/59 projects; of which the Ministry of Industry and Trade has approved provisional prices for 51 projects.

19 projects have been accepted by competent State management agencies for the entire plant/part of the plant; 27 projects have been granted electricity operation licenses for the entire plant/part of the plant; 36 projects have had decisions to extend investment policies.

Thus, there are still 15 projects with a total capacity of 882.70 MW that have not yet submitted negotiation documents.

EVN continues to request investors of the remaining renewable energy projects to submit documents as soon as possible so that this unit can consider temporary price agreements for the plants. After negotiations are completed, the agreed price will be settled according to the official price from the date of electricity generation to the grid. For projects that have completed investment and construction work, complete legal documents according to regulations.

PHAM DUY


Useful

Emotion

Creative

Unique



Source

Comment (0)

No data
No data

Same tag

Same category

Explore Lo Go - Xa Mat National Park
Quang Nam - Tam Tien fish market in the South
Indonesia fired 7 cannon shots to welcome General Secretary To Lam and his wife.
Admire the state-of-the-art equipment and armored vehicles displayed by the Ministry of Public Security on the streets of Hanoi

Same author

Heritage

Figure

Business

No videos available

News

Ministry - Branch

Local

Product